1901-1903 S MARVIN AVE 90016

Certificate Information: 1901-1903 S MARVIN AVE 90016

Application / Permit
21010-30000-00952
Plan Check / Job No.
B21WL00879
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2 STORY DUPLEX, EACH W/2-CAR GARAGE AND ROOF TRUSSES
Permit Issued
Issued on 9/28/2021
Issuing Office
Current Status
CofO Issued on 3/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2021 APPLICANT
Assigned to Plan Check Engineer 3/17/2021 VLADIMIR ARUTYUNYAN
Corrections Issued 4/16/2021 VLADIMIR ARUTYUNYAN
Quality Review Completed 4/16/2021 KAMRAN GHOTBI RAVANDI
Plan Check Approved 9/15/2021 VLADIMIR ARUTYUNYAN
Issued 9/28/2021 APPLICANT
CofO in Progress 3/14/2023 JOSE AVILA
Permit Finaled 3/18/2023 DEROLD HAUFF
CofO Issued 3/18/2023 DEROLD HAUFF
Permit Finaled 3/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/27/2021 WALLIE JONG
Highway dedication Cleared 4/27/2021 WALLIE JONG
Permit Cleared 4/27/2021 WALLIE JONG
Sewer availability Cleared 4/27/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/28/2021 WALLIE JONG
Trees in Parkway Cleared 5/13/2021 JOHN KIM
Hydrant and Access approval Cleared 6/4/2021 JOHN CONNEALLY
Low Impact Development Cleared 8/27/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/31/2021 RENZ SORIANO

Contact Information

Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/25/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 11/15/2021 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 11/22/2021 Approved JOSE AVILA
Underground Mechanical 12/1/2021 Approved JOSE AVILA
Deputy Reinf. Concrete 12/2/2021 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/4/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 2/1/2022 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/1/2022 Approved JOSE AVILA
ELECTRICAL-Rough 2/9/2022 Approved JOSE AVILA
Gas Test 2/9/2022 Partial Approval JOSE AVILA
HVAC-Rough 2/9/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 2/9/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/15/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 2/17/2022 Approved JOSE AVILA
HVAC-Rough 2/17/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 2/17/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 3/2/2022 Corrections Issued JOSE AVILA
Green Building Rough 3/2/2022 Corrections Issued JOSE AVILA
Verify Sprinkler Sign Off 3/2/2022 Corrections Issued JOSE AVILA
HVAC-Rough 3/16/2022 Approved JOSE AVILA
Verify Sprinkler Sign Off 3/16/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 3/21/2022 Partial Approval JOSE AVILA
Insulation 3/22/2022 Approved JOSE AVILA
Interior/Exterior Lathing 3/30/2022 Approved JOSE AVILA
Shower Pan 3/30/2022 Approved JOSE AVILA
Drywall Nailing 4/1/2022 Approved JOSE AVILA
ELECTRICAL-Final 7/19/2022 Corrections Issued JOSE AVILA
HVAC-Final 7/19/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 7/19/2022 Corrections Issued JOSE AVILA
Service/Power Release 7/19/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 8/23/2022 Approved JOSE AVILA
ELECTRICAL-Final 9/8/2022 Corrections Issued JOSE AVILA
HVAC-Final 9/8/2022 Approved JOSE AVILA
Service/Power Release 9/8/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Final 12/22/2022 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 2/2/2023 Partial Approval JOSE AVILA
ELECTRICAL-Final 2/2/2023 Approved JOSE AVILA
Green Building Final 2/2/2023 Approved JOSE AVILA
Green Building Rough 2/2/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/2/2023 SGSOV Approved JOSE AVILA
Service/Power Release 2/2/2023 Approved JOSE AVILA
Smoke Detectors 2/2/2023 Approved JOSE AVILA
Verify Sprinkler Sign Off 2/2/2023 Approved JOSE AVILA
ELECTRICAL-Final 3/2/2023 Approved JOSE AVILA
Final 3/2/2023 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 3/6/2023 Approved JOSE AVILA
Final 3/14/2023 OK to Issue CofO JOSE AVILA