1901-1903 S MARVIN AVE 90016
Certificate Information: 1901-1903 S MARVIN AVE 90016
- Application / Permit
- 21010-30000-00952
- Plan Check / Job No.
- B21WL00879
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 2 STORY DUPLEX, EACH W/2-CAR GARAGE AND ROOF TRUSSES
- Permit Issued
- Issued on 9/28/2021
- Issuing Office
- Current Status
- CofO Issued on 3/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2021 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 4/16/2021 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 4/16/2021 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 9/15/2021 | VLADIMIR ARUTYUNYAN |
| Issued | 9/28/2021 | APPLICANT |
| CofO in Progress | 3/14/2023 | JOSE AVILA |
| Permit Finaled | 3/18/2023 | DEROLD HAUFF |
| CofO Issued | 3/18/2023 | DEROLD HAUFF |
| Permit Finaled | 3/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/27/2021 | WALLIE JONG |
| Highway dedication | Cleared | 4/27/2021 | WALLIE JONG |
| Permit | Cleared | 4/27/2021 | WALLIE JONG |
| Sewer availability | Cleared | 4/27/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2021 | WALLIE JONG |
| Trees in Parkway | Cleared | 5/13/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 6/4/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 8/27/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/31/2021 | RENZ SORIANO |
Contact Information
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/25/2021 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/15/2021 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 11/22/2021 | Approved | JOSE AVILA |
| Underground Mechanical | 12/1/2021 | Approved | JOSE AVILA |
| Deputy Reinf. Concrete | 12/2/2021 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 2/1/2022 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 2/9/2022 | Approved | JOSE AVILA |
| Gas Test | 2/9/2022 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 2/9/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 2/9/2022 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 2/17/2022 | Approved | JOSE AVILA |
| HVAC-Rough | 2/17/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 2/17/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 3/2/2022 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 3/2/2022 | Corrections Issued | JOSE AVILA |
| Verify Sprinkler Sign Off | 3/2/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 3/16/2022 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 3/16/2022 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 3/21/2022 | Partial Approval | JOSE AVILA |
| Insulation | 3/22/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 3/30/2022 | Approved | JOSE AVILA |
| Shower Pan | 3/30/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 4/1/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 7/19/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 7/19/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 7/19/2022 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 7/19/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 8/23/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 9/8/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 9/8/2022 | Approved | JOSE AVILA |
| Service/Power Release | 9/8/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 12/22/2022 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 2/2/2023 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Final | 2/2/2023 | Approved | JOSE AVILA |
| Green Building Final | 2/2/2023 | Approved | JOSE AVILA |
| Green Building Rough | 2/2/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 2/2/2023 | Approved | JOSE AVILA |
| Smoke Detectors | 2/2/2023 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 2/2/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 3/2/2023 | Approved | JOSE AVILA |
| Final | 3/2/2023 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 3/6/2023 | Approved | JOSE AVILA |
| Final | 3/14/2023 | OK to Issue CofO | JOSE AVILA |