1207-1209 N COMMONWEALTH AVE 90029
Certificate Information: 1207-1209 N COMMONWEALTH AVE 90029
- Application / Permit
- 21010-30000-00686
- Plan Check / Job No.
- B21WL00628
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 2 story duplex with roof trusses & attached 4 car garage.
- Permit Issued
- Issued on 7/22/2021
- Issuing Office
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2021 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 3/22/2021 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 3/25/2021 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 7/14/2021 | VLADIMIR ARUTYUNYAN |
| Issued | 7/22/2021 | APPLICANT |
| CofO in Progress | 11/18/2022 | FREDDIE RIVERA |
| No Progress | 1/25/2023 | FREDDIE RIVERA |
| CofO in Progress | 9/19/2023 | FREDDIE RIVERA |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
| CofO Issued | 9/21/2023 | DEROLD HAUFF |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/12/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2021 | JEANIE LAM |
| Permit | Cleared | 4/12/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/12/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 5/10/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 5/14/2021 | ROSA SILVA |
| Trees in Parkway | Cleared | 6/28/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 6/29/2021 | KURT CORRAL |
| GPI Written Notices | Cleared | 7/14/2021 | VLADIMIR ARUTYUNYAN |
| Grading Pre-Inspection | Cleared | 7/14/2021 | VLADIMIR ARUTYUNYAN |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/12/2021 | Approved | CALEB MEISTER |
| Underground Mechanical | 8/12/2021 | Approved | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 8/25/2021 | Approved | ROBERT VORHIS |
| Special/Order Compliance | 9/23/2021 | Approved | ASHLEY THOMPSON |
| Underground Mechanical | 9/29/2021 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2021 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2021 | Partial Inspection | ROBERT VORHIS |
| Deputy Wood Construction | 11/12/2021 | No Access for Inspection | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2021 | Approved | ROBERT VORHIS |
| ELECTRICAL-Rough | 12/9/2021 | Approved | STUART CHAPMAN |
| HVAC-Rough | 12/9/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 12/9/2021 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/29/2021 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 12/29/2021 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 12/29/2021 | Corrections Issued | JOSE AVILA |
| Verify Sprinkler Sign Off | 12/29/2021 | Approved | JOSE AVILA |
| PLUMBING-Rough | 1/5/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 3/11/2022 | Partial Approval | AMY COLIN |
| Green Building Rough | 3/11/2022 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 3/11/2022 | Partial Approval | AMY COLIN |
| Drywall Nailing | 4/7/2022 | Partial Approval | FREDDIE RIVERA |
| Insulation | 4/18/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 4/22/2022 | Conditional Approval | ADAM ESCOTO |
| Drywall Nailing | 4/25/2022 | No Access for Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 4/29/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 8/11/2022 | Approved | FREDDIE RIVERA |
| HVAC-Final | 10/12/2022 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 10/12/2022 | Approved | FREDDIE RIVERA |
| HVAC-Final | 10/14/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 10/14/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/4/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 11/4/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 11/4/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 11/4/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 11/4/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 11/4/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 11/4/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 11/14/2022 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 11/14/2022 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/14/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 11/14/2022 | Partial Inspection | FREDDIE RIVERA |
| Final | 11/17/2022 | OK to Issue CofO | FREDDIE RIVERA |
| Green Building Final | 11/17/2022 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 11/17/2022 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 1/25/2023 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Final | 9/12/2023 | Approved | FREDDIE RIVERA |
| Final | 9/12/2023 | Conditional Approval | FREDDIE RIVERA |