1207-1209 N COMMONWEALTH AVE 90029

Certificate Information: 1207-1209 N COMMONWEALTH AVE 90029

Application / Permit
21010-30000-00686
Plan Check / Job No.
B21WL00628
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 2 story duplex with roof trusses & attached 4 car garage.
Permit Issued
Issued on 7/22/2021
Issuing Office
Current Status
CofO Issued on 9/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2021 APPLICANT
Assigned to Plan Check Engineer 2/24/2021 VLADIMIR ARUTYUNYAN
Corrections Issued 3/22/2021 VLADIMIR ARUTYUNYAN
Quality Review Completed 3/25/2021 KAMRAN GHOTBI RAVANDI
Plan Check Approved 7/14/2021 VLADIMIR ARUTYUNYAN
Issued 7/22/2021 APPLICANT
CofO in Progress 11/18/2022 FREDDIE RIVERA
No Progress 1/25/2023 FREDDIE RIVERA
CofO in Progress 9/19/2023 FREDDIE RIVERA
Permit Finaled 9/21/2023 DEROLD HAUFF
CofO Issued 9/21/2023 DEROLD HAUFF
Permit Finaled 9/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/12/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/12/2021 JEANIE LAM
Permit Cleared 4/12/2021 JEANIE LAM
Sewer availability Cleared 4/12/2021 JEANIE LAM
Low Impact Development Cleared 5/10/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 5/14/2021 ROSA SILVA
Trees in Parkway Cleared 6/28/2021 JOHN KIM
Hydrant and Access approval Cleared 6/29/2021 KURT CORRAL
GPI Written Notices Cleared 7/14/2021 VLADIMIR ARUTYUNYAN
Grading Pre-Inspection Cleared 7/14/2021 VLADIMIR ARUTYUNYAN

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/12/2021 Approved CALEB MEISTER
Underground Mechanical 8/12/2021 Approved CALEB MEISTER
Excavation/Setback/Form/Re-Bar 8/25/2021 Approved ROBERT VORHIS
Special/Order Compliance 9/23/2021 Approved ASHLEY THOMPSON
Underground Mechanical 9/29/2021 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Partial Approval ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 11/9/2021 Partial Inspection ROBERT VORHIS
Deputy Wood Construction 11/12/2021 No Access for Inspection JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Approved ROBERT VORHIS
ELECTRICAL-Rough 12/9/2021 Approved STUART CHAPMAN
HVAC-Rough 12/9/2021 Approved STUART CHAPMAN
PLUMBING-Rough 12/9/2021 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 12/29/2021 Corrections Issued JOSE AVILA
Green Building Rough 12/29/2021 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 12/29/2021 Corrections Issued JOSE AVILA
Verify Sprinkler Sign Off 12/29/2021 Approved JOSE AVILA
PLUMBING-Rough 1/5/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 3/11/2022 Partial Approval AMY COLIN
Green Building Rough 3/11/2022 Approved AMY COLIN
Interior/Exterior Lathing 3/11/2022 Partial Approval AMY COLIN
Drywall Nailing 4/7/2022 Partial Approval FREDDIE RIVERA
Insulation 4/18/2022 Approved FREDDIE RIVERA
Drywall Nailing 4/22/2022 Conditional Approval ADAM ESCOTO
Drywall Nailing 4/25/2022 No Access for Inspection FREDDIE RIVERA
Interior/Exterior Lathing 4/29/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 8/11/2022 Approved FREDDIE RIVERA
HVAC-Final 10/12/2022 Corrections Issued FREDDIE RIVERA
HVAC-Rough 10/12/2022 Approved FREDDIE RIVERA
HVAC-Final 10/14/2022 Approved FREDDIE RIVERA
PLUMBING-Final 10/14/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 11/4/2022 Approved ALIZAH MAYAGOITIA
Final 11/4/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 11/4/2022 Approved ALIZAH MAYAGOITIA
Green Building Final 11/4/2022 Partial Approval ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 11/4/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 11/4/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 11/4/2022 Approved ALIZAH MAYAGOITIA
Final 11/14/2022 Partial Inspection FREDDIE RIVERA
Green Building Final 11/14/2022 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/14/2022 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 11/14/2022 Partial Inspection FREDDIE RIVERA
Final 11/17/2022 OK to Issue CofO FREDDIE RIVERA
Green Building Final 11/17/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/17/2022 SGSOV Approved FREDDIE RIVERA
Service/Power Release 11/17/2022 Approved FREDDIE RIVERA
Special/Order Compliance 1/25/2023 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Final 9/12/2023 Approved FREDDIE RIVERA
Final 9/12/2023 Conditional Approval FREDDIE RIVERA