1417 S DOHENY DR 90035
Certificate Information: 1417 S DOHENY DR 90035
- Application / Permit
- 21010-30000-00608
- Plan Check / Job No.
- B21WL00554
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) 4-story SFD WITH ATTACHED 2-CAR GARAGE AND ROOFTOP DECK, LOT D "SAMLL LOT SUBDIVISION PURSUANT TO PRELIMINARY PARCEL MAP No. AA-2020-1495-PMLA-SL-HCA. A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED"
- Permit Issued
- Issued on 4/21/2022
- Issuing Office
- Current Status
- CofO Issued on 2/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2021 | TARIK SAOUD |
| Corrections Issued | 3/15/2021 | TARIK SAOUD |
| Quality Review Completed | 3/24/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/23/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 2/16/2022 | TARIK SAOUD |
| Building Plans Picked Up | 2/17/2022 | APPLICANT |
| Plan Check Approved | 3/16/2022 | TARIK SAOUD |
| Issued | 4/21/2022 | APPLICANT |
| CofO in Progress | 2/7/2025 | ASHLEY THOMPSON |
| Permit Finaled | 2/11/2025 | RICHARD STEINBACH |
| CofO Issued | 2/11/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/11/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/27/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 6/1/2021 | HISASHI KOBAYAKAWA |
| Trees in Parkway | Cleared | 6/8/2021 | JOHN KIM |
| Frnt yard landscape/Water mgmt | Cleared | 6/11/2021 | ANACANY HURTADO |
| ZA Case | Cleared | 6/11/2021 | ANACANY HURTADO |
| ZA Case | Cleared | 6/11/2021 | ANACANY HURTADO |
| Miscellaneous | Cleared | 6/22/2021 | RAYMOND MUGAMBWA |
| Permit | Cleared | 6/22/2021 | RAYMOND MUGAMBWA |
| Low Impact Development | Cleared | 10/28/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/2/2021 | RAYMOND MUGAMBWA |
| Abandoned oil well | Cleared | 1/8/2022 | ROBERT DUFF |
| Hydrant and Access approval | Cleared | 2/14/2022 | JOHN CONNEALLY |
| Building over 36-ft | Cleared | 2/16/2022 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 2/16/2022 | TARIK SAOUD |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Simgel Co Inc; Lic. No.: 638371-B | 2035 WESTWOOD BLVD SUITE 212 LOS ANGELES, CA 90025 |
| Engineer | Berkoz,, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 7/26/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Deputy Reinf. Concrete | 7/27/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 8/26/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 8/26/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/26/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 8/29/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Underground Mechanical | 8/29/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Special/Order Compliance | 9/20/2022 | Not Ready for Inspection | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 9/22/2022 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 9/22/2022 | Partial Approval | MICHAEL PELHAM |
| METHANE-Barrier | 9/22/2022 | Not Ready for Inspection | MICHAEL PELHAM |
| METHANE-Subgrade | 9/22/2022 | Corrections Issued | MICHAEL PELHAM |
| Footing/Foundation/Slab | 10/27/2022 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 11/4/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Methane Barrier | 11/17/2022 | Partial Approval | MICHAEL PELHAM |
| Deputy Methane Barrier | 11/18/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Methane Barrier | 11/21/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/30/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Barrier | 11/30/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 11/30/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 12/2/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2023 | Corrections Issued | DAVID FEILER |
| Drywall Nailing | 2/15/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Special/Order Compliance | 2/15/2023 | Partial Inspection | DAVID FEILER |
| Deputy Wood Construction | 2/24/2023 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Drywall Nailing | 3/3/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2023 | Partial Approval | ASHLEY THOMPSON |
| Drywall Nailing | 3/10/2023 | Partial Approval | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2023 | Partial Approval | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2023 | Partial Approval | ASHLEY THOMPSON |
| Drywall Nailing | 3/24/2023 | Corrections Issued | ASHLEY THOMPSON |
| Deputy Wood Construction | 4/21/2023 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2023 | Corrections Issued | CLAYTON GRAHAM |
| Deputy Wood Construction | 4/26/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Drywall Nailing | 5/1/2023 | Partial Approval | CLAYTON GRAHAM |
| Deputy Wood Construction | 5/19/2023 | Conditional Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2023 | Partial Approval | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2023 | Partial Approval | JEREMY TODD |
| Drywall Nailing | 6/5/2023 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Wood Construction | 6/22/2023 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2023 | Partial Approval | JEREMY TODD |
| Final | 6/26/2023 | Corrections Issued | CLAYTON GRAHAM |
| Underground Mechanical | 6/29/2023 | Partial Approval | CLAYTON GRAHAM |
| Underground Mechanical | 7/17/2023 | Corrections Issued | CLAYTON GRAHAM |
| Underground Mechanical | 7/18/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 8/16/2023 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 8/31/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 8/31/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 8/31/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Special/Order Compliance | 8/31/2023 | Partial Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 9/20/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 9/20/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 9/29/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 9/29/2023 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 9/29/2023 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 9/29/2023 | Partial Approval | MEL KHACHATOURIAN |
| METHANE-Rough | 9/29/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 9/29/2023 | Partial Approval | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 9/29/2023 | Approved | MEL KHACHATOURIAN |
| Wood Frame | 9/29/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Wood Frame | 10/5/2023 | Approved | MEL KHACHATOURIAN |
| Insulation | 10/23/2023 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/27/2023 | Partial Approval | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 10/30/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 11/3/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Rough | 11/7/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 11/7/2023 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 11/7/2023 | Approved | OGANES TARAKHCHYAN |
| Insulation | 11/14/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 11/14/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 11/30/2023 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 12/12/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 12/12/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Shower Pan | 12/14/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 12/27/2023 | Partial Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 1/5/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/2/2024 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 4/9/2024 | Approved | OGANES TARAKHCHYAN |
| Sewer | 4/25/2024 | Approved | MEL KHACHATOURIAN |
| Underground Mechanical | 4/25/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 5/29/2024 | Corrections Issued | ASHLEY THOMPSON |
| Gas Test | 6/4/2024 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Final | 6/4/2024 | Not Ready for Inspection | JESUS PINEDA |
| Gas Test | 6/6/2024 | Approved | SEAN HAUPT |
| PLUMBING-Final | 6/6/2024 | Approved | SEAN HAUPT |
| HVAC-Final | 6/26/2024 | Corrections Issued | SEAN HAUPT |
| HVAC-Final | 7/15/2024 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Final | 7/17/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 12/24/2024 | Approved | ARAM AVEDISIAN |
| Final | 12/24/2024 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 12/24/2024 | Approved | ARAM AVEDISIAN |
| METHANE-Final | 12/24/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| METHANE-Rough | 12/24/2024 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 12/24/2024 | SGSOV Not Ready | ARAM AVEDISIAN |
| Service/Power Release | 12/24/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 12/24/2024 | Approved | ARAM AVEDISIAN |
| Structural Steel Frame | 12/24/2024 | Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 12/26/2024 | Corrections Issued | ASHLEY THOMPSON |
| Final | 12/30/2024 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Final | 12/30/2024 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 12/30/2024 | SGSOV Approved | STEPHANIE SWANSON |
| Service/Power Release | 12/30/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Service/Power Release | 1/9/2025 | Approved | DAVID FEILER |
| Final | 2/7/2025 | OK to Issue CofO | ASHLEY THOMPSON |