1417 S DOHENY DR 90035

Certificate Information: 1417 S DOHENY DR 90035

Application / Permit
21010-30000-00608
Plan Check / Job No.
B21WL00554
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(n) 4-story SFD WITH ATTACHED 2-CAR GARAGE AND ROOFTOP DECK, LOT D "SAMLL LOT SUBDIVISION PURSUANT TO PRELIMINARY PARCEL MAP No. AA-2020-1495-PMLA-SL-HCA. A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED"
Permit Issued
Issued on 4/21/2022
Issuing Office
Current Status
CofO Issued on 2/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2021 APPLICANT
Assigned to Plan Check Engineer 3/5/2021 TARIK SAOUD
Corrections Issued 3/15/2021 TARIK SAOUD
Quality Review Completed 3/24/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/23/2021 TARIK SAOUD
Applicant returned to address corrections 2/16/2022 TARIK SAOUD
Building Plans Picked Up 2/17/2022 APPLICANT
Plan Check Approved 3/16/2022 TARIK SAOUD
Issued 4/21/2022 APPLICANT
CofO in Progress 2/7/2025 ASHLEY THOMPSON
Permit Finaled 2/11/2025 RICHARD STEINBACH
CofO Issued 2/11/2025 RICHARD STEINBACH
Permit Finaled 2/11/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/27/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 6/1/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 6/1/2021 HISASHI KOBAYAKAWA
Trees in Parkway Cleared 6/8/2021 JOHN KIM
Frnt yard landscape/Water mgmt Cleared 6/11/2021 ANACANY HURTADO
ZA Case Cleared 6/11/2021 ANACANY HURTADO
ZA Case Cleared 6/11/2021 ANACANY HURTADO
Miscellaneous Cleared 6/22/2021 RAYMOND MUGAMBWA
Permit Cleared 6/22/2021 RAYMOND MUGAMBWA
Low Impact Development Cleared 10/28/2021 TA ANH
Roof/Waste drainage to street Cleared 11/2/2021 RAYMOND MUGAMBWA
Abandoned oil well Cleared 1/8/2022 ROBERT DUFF
Hydrant and Access approval Cleared 2/14/2022 JOHN CONNEALLY
Building over 36-ft Cleared 2/16/2022 CALOSHA APPROVED
Grading Pre-Inspection Cleared 2/16/2022 TARIK SAOUD

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Simgel Co Inc; Lic. No.: 638371-B 2035 WESTWOOD BLVD SUITE 212      LOS ANGELES, CA 90025
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 7/26/2022 Not Ready for Inspection JOHN KIDWELL
Deputy Reinf. Concrete 7/27/2022 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 8/26/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 8/26/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 8/26/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 8/29/2022 Corrections Issued OGANES TARAKHCHYAN
Underground Mechanical 8/29/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Special/Order Compliance 9/20/2022 Not Ready for Inspection MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 9/22/2022 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 9/22/2022 Partial Approval MICHAEL PELHAM
METHANE-Barrier 9/22/2022 Not Ready for Inspection MICHAEL PELHAM
METHANE-Subgrade 9/22/2022 Corrections Issued MICHAEL PELHAM
Footing/Foundation/Slab 10/27/2022 Partial Approval OGANES TARAKHCHYAN
METHANE-Subgrade 11/4/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Deputy Methane Barrier 11/17/2022 Partial Approval MICHAEL PELHAM
Deputy Methane Barrier 11/18/2022 Conditional Approval MICHAEL PELHAM
Deputy Methane Barrier 11/21/2022 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 11/30/2022 Approved OGANES TARAKHCHYAN
METHANE-Barrier 11/30/2022 Approved OGANES TARAKHCHYAN
METHANE-Subgrade 11/30/2022 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 12/2/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/3/2023 Corrections Issued DAVID FEILER
Drywall Nailing 2/15/2023 Not Ready for Inspection ASHLEY THOMPSON
Special/Order Compliance 2/15/2023 Partial Inspection DAVID FEILER
Deputy Wood Construction 2/24/2023 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 2/27/2023 Not Ready for Inspection ASHLEY THOMPSON
Drywall Nailing 3/3/2023 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 3/3/2023 Partial Approval ASHLEY THOMPSON
Drywall Nailing 3/10/2023 Partial Approval JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 3/14/2023 Partial Approval JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Partial Approval ASHLEY THOMPSON
Drywall Nailing 3/24/2023 Corrections Issued ASHLEY THOMPSON
Deputy Wood Construction 4/21/2023 Approved CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Corrections Issued CLAYTON GRAHAM
Deputy Wood Construction 4/26/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 4/27/2023 Not Ready for Inspection CLAYTON GRAHAM
Drywall Nailing 5/1/2023 Partial Approval CLAYTON GRAHAM
Deputy Wood Construction 5/19/2023 Conditional Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Partial Approval JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 6/1/2023 Partial Approval JEREMY TODD
Drywall Nailing 6/5/2023 Partial Approval CHRISTOPHER WILSON
Deputy Wood Construction 6/22/2023 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 6/23/2023 Partial Approval JEREMY TODD
Final 6/26/2023 Corrections Issued CLAYTON GRAHAM
Underground Mechanical 6/29/2023 Partial Approval CLAYTON GRAHAM
Underground Mechanical 7/17/2023 Corrections Issued CLAYTON GRAHAM
Underground Mechanical 7/18/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Rough 8/16/2023 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 8/31/2023 Corrections Issued CLAYTON GRAHAM
HVAC-Rough 8/31/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Rough 8/31/2023 Not Ready for Inspection CLAYTON GRAHAM
Special/Order Compliance 8/31/2023 Partial Inspection BEN MOLSTAD
ELECTRICAL-Rough 9/20/2023 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 9/20/2023 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 9/29/2023 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 9/29/2023 Partial Approval MEL KHACHATOURIAN
Green Building Rough 9/29/2023 Approved MEL KHACHATOURIAN
HVAC-Rough 9/29/2023 Partial Approval MEL KHACHATOURIAN
METHANE-Rough 9/29/2023 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 9/29/2023 Partial Approval MEL KHACHATOURIAN
Verify Sprinkler Sign Off 9/29/2023 Approved MEL KHACHATOURIAN
Wood Frame 9/29/2023 Not Ready for Inspection MEL KHACHATOURIAN
Wood Frame 10/5/2023 Approved MEL KHACHATOURIAN
Insulation 10/23/2023 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 10/27/2023 Partial Approval CLAYTON GRAHAM
ELECTRICAL-Rough 10/30/2023 Corrections Issued CLAYTON GRAHAM
ELECTRICAL-Rough 11/3/2023 Approved CLAYTON GRAHAM
HVAC-Rough 11/7/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 11/7/2023 Approved OGANES TARAKHCHYAN
Wood Frame 11/7/2023 Approved OGANES TARAKHCHYAN
Insulation 11/14/2023 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 11/14/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Drywall Nailing 11/30/2023 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 12/12/2023 Partial Approval OGANES TARAKHCHYAN
Shower Pan 12/12/2023 Corrections Issued OGANES TARAKHCHYAN
Shower Pan 12/14/2023 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 12/27/2023 Partial Approval MEL KHACHATOURIAN
Interior/Exterior Lathing 1/5/2024 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/2/2024 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Final 4/9/2024 Approved OGANES TARAKHCHYAN
Sewer 4/25/2024 Approved MEL KHACHATOURIAN
Underground Mechanical 4/25/2024 Approved MEL KHACHATOURIAN
PLUMBING-Final 5/29/2024 Corrections Issued ASHLEY THOMPSON
Gas Test 6/4/2024 Not Ready for Inspection JESUS PINEDA
PLUMBING-Final 6/4/2024 Not Ready for Inspection JESUS PINEDA
Gas Test 6/6/2024 Approved SEAN HAUPT
PLUMBING-Final 6/6/2024 Approved SEAN HAUPT
HVAC-Final 6/26/2024 Corrections Issued SEAN HAUPT
HVAC-Final 7/15/2024 Partial Approval STEPHANIE SWANSON
HVAC-Final 7/17/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 12/24/2024 Approved ARAM AVEDISIAN
Final 12/24/2024 Corrections Issued ARAM AVEDISIAN
Green Building Final 12/24/2024 Approved ARAM AVEDISIAN
METHANE-Final 12/24/2024 Not Ready for Inspection ARAM AVEDISIAN
METHANE-Rough 12/24/2024 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 12/24/2024 SGSOV Not Ready ARAM AVEDISIAN
Service/Power Release 12/24/2024 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 12/24/2024 Approved ARAM AVEDISIAN
Structural Steel Frame 12/24/2024 Approved ARAM AVEDISIAN
Special/Order Compliance 12/26/2024 Corrections Issued ASHLEY THOMPSON
Final 12/30/2024 Corrections Issued STEPHANIE SWANSON
METHANE-Final 12/30/2024 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 12/30/2024 SGSOV Approved STEPHANIE SWANSON
Service/Power Release 12/30/2024 Not Ready for Inspection STEPHANIE SWANSON
Service/Power Release 1/9/2025 Approved DAVID FEILER
Final 2/7/2025 OK to Issue CofO ASHLEY THOMPSON