4454 N TOBIAS AVE 91403
Certificate Information: 4454 N TOBIAS AVE 91403
- Application / Permit
- 21010-30000-00556
- Plan Check / Job No.
- B21WL00488
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER STATE CODE
- Permit Issued
- Issued on 12/9/2021
- Issuing Office
- Current Status
- CofO Issued on 2/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2021 | TARIK SAOUD |
| Corrections Issued | 2/22/2021 | TARIK SAOUD |
| Quality Review Completed | 3/10/2021 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 11/24/2021 | TARIK SAOUD |
| Issued | 12/9/2021 | APPLICANT |
| Building Plans Picked Up | 2/3/2022 | APPLICANT |
| CofO in Progress | 1/2/2024 | MISAEL ESPARZA |
| Permit Finaled | 2/9/2024 | RUBEN SALAS |
| CofO Issued | 2/9/2024 | RUBEN SALAS |
| Permit Finaled | 2/9/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/26/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/29/2021 | JOHN TRIANTAFYLLOS |
| ZI | Cleared | 6/22/2021 | LOUIS ORTEGA |
| Hydrant and Access approval | Cleared | 7/16/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 8/27/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 9/22/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 11/16/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Potkin Brian Edward; Lic. No.: 470714-B | 14011 VENTURA BLVD #204 SHERMAN OAKS, CA 91423 |
| Engineer | Azarbin,, Hamid; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
| Engineer | Mirzadeh,, Amir; Lic. No.: C58119 | P O BOX 572110 TARZANA, CA 91357 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/8/2022 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 3/8/2022 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/18/2022 | Partial Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 7/15/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | Corrections Issued | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2022 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 8/25/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 8/25/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/12/2022 | Corrections Issued | MISAEL ESPARZA |
| Gas Test | 9/12/2022 | Corrections Issued | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 9/12/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Sewer | 9/12/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/20/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 9/20/2022 | SGSOV Not Ready | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/28/2022 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 11/28/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/28/2022 | Partial Approval | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 11/28/2022 | Approved | MISAEL ESPARZA |
| Wood Frame | 11/28/2022 | Partial Approval | MISAEL ESPARZA |
| Insulation | 12/19/2022 | Conditional Approval | MISAEL ESPARZA |
| Drywall Nailing | 12/29/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/1/2023 | Approved | MISAEL ESPARZA |
| Shower Pan | 3/1/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 10/16/2023 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 10/16/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 10/31/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 10/31/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 10/31/2023 | Corrections Issued | MISAEL ESPARZA |
| Smoke Detectors | 10/31/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/7/2023 | Approved | MISAEL ESPARZA |
| HVAC-Final | 11/7/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 11/7/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/7/2023 | No Access for Inspection | MISAEL ESPARZA |
| Final | 12/7/2023 | No Access for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 12/7/2023 | No Access for Inspection | MISAEL ESPARZA |
| Green Building Final | 12/7/2023 | No Access for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 12/7/2023 | No Access for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/7/2023 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 12/7/2023 | No Access for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/22/2023 | Approved | MISAEL ESPARZA |
| Final | 12/22/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Footing/Foundation/Slab | 12/22/2023 | Approved | MISAEL ESPARZA |
| Green Building Final | 12/22/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/22/2023 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 12/22/2023 | Approved | MISAEL ESPARZA |
| Service/Power Release | 1/25/2024 | Approved | MISAEL ESPARZA |