11620 W CLARKSON ROAD 90064

Certificate Information: 11620 W CLARKSON ROAD 90064

Application / Permit
21010-30000-00473
Plan Check / Job No.
B21WL00425
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-Story S.F.D w/Attached Garage and Roof Top Deck
Permit Issued
Issued on 5/3/2022
Issuing Office
Current Status
CofO Issued on 6/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 DAVID CASTILLO
Corrections Issued 2/16/2021 DAVID CASTILLO
Quality Review Completed 2/25/2021 TARIK SAOUD
Applicant returned to address corrections 11/4/2021 DAVID CASTILLO
Plan Check Approved 2/16/2022 DAVID CASTILLO
Building Plans Picked Up 2/17/2022 APPLICANT
Issued 5/3/2022 APPLICANT
CofO in Progress 6/20/2024 MICHAEL PELHAM
Permit Finaled 6/26/2024 DANIEL ORRANTE
CofO Issued 6/26/2024 DANIEL ORRANTE
Permit Finaled 6/26/2024 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 3/12/2021 EILEEN HUNT
Eng Process Fee Ord 176,300 Cleared 3/22/2021 CATHERINE ADROVER
Hydrant and Access approval Cleared 4/13/2021 MATTHEW CRAIG
Sewer availability Cleared 8/10/2021 CATHERINE ADROVER
Low Impact Development Cleared 10/14/2021 LONDY ALVARADO
Roof/Waste drainage to street Cleared 10/23/2021 THOMAS LANG

Contact Information

Contractor Zohrabians Construction Company; Lic. No.: 1075123-B 1367 FOOTHILL BLVD      LA CANADA FLINTRIDGE, CA 91011
Engineer Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/10/2022 Partial Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 6/30/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 8/4/2022 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 1/10/2023 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 1/11/2023 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 1/19/2023 Corrections Issued JOHNNY MIRANDA
Deputy Wood Construction 1/20/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 1/25/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 3/6/2023 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 3/6/2023 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 3/6/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 3/23/2023 Not Ready for Inspection HERBERT GIRON
Insulation 3/23/2023 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 3/23/2023 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 3/29/2023 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 3/29/2023 Approved JOHNNY MIRANDA
Green Building Rough 3/29/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 3/29/2023 Approved JOHNNY MIRANDA
Insulation 3/29/2023 Partial Approval JOHNNY MIRANDA
Interior/Exterior Lathing 3/29/2023 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 3/29/2023 Not Ready for Inspection JOHNNY MIRANDA
Verify Sprinkler Sign Off 3/29/2023 Approved JOHNNY MIRANDA
Drywall Nailing 4/24/2023 Partial Approval HERBERT GIRON
Final 4/24/2023 Corrections Issued HERBERT GIRON
Sewer 6/1/2023 Approved JOHNNY MIRANDA
Underground Mechanical 6/1/2023 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 8/3/2023 Approved JESUS PINEDA
Green Building Rough 8/3/2023 Approved JESUS PINEDA
Insulation 8/3/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 8/3/2023 Corrections Issued JESUS PINEDA
Drywall Nailing 8/5/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 8/5/2023 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Final 11/3/2023 Corrections Issued JESUS PINEDA
PLUMBING-Final 11/3/2023 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 11/3/2023 SGSOV Approved JESUS PINEDA
Smoke Detectors 11/3/2023 Approved JESUS PINEDA
ELECTRICAL-Final 12/5/2023 No Access for Inspection JESUS PINEDA
HVAC-Final 12/5/2023 Corrections Issued JESUS PINEDA
PLUMBING-Final 12/5/2023 No Access for Inspection JESUS PINEDA
ELECTRICAL-Final 12/7/2023 Conditional Approval KENNETH NAGLE
HVAC-Final 12/7/2023 Corrections Issued KENNETH NAGLE
Final 2/23/2024 Corrections Issued JESUS PINEDA
Gas Test 2/23/2024 Corrections Issued JESUS PINEDA
HVAC-Final 2/23/2024 Approved JESUS PINEDA
PLUMBING-Final 2/23/2024 Approved JESUS PINEDA
Service/Power Release 3/18/2024 Approved KENNETH NAGLE
Final 5/6/2024 Not Ready for Inspection JESUS PINEDA
Footing/Foundation/Slab 5/6/2024 Approved JESUS PINEDA
Green Building Final 5/6/2024 Approved JESUS PINEDA
Final 5/9/2024 Corrections Issued JESUS PINEDA
Final 6/20/2024 OK to Issue CofO MICHAEL PELHAM