10503 W ROUNTREE ROAD 90064
Certificate Information: 10503 W ROUNTREE ROAD 90064
- Application / Permit
- 21010-30000-00328
- Plan Check / Job No.
- B21WL00286
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) 2-story SFD wih 2-car garage
- Permit Issued
- Issued on 7/2/2021
- Issuing Office
- Current Status
- CofO Issued on 8/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2021 | TARIK SAOUD |
| Corrections Issued | 2/1/2021 | TARIK SAOUD |
| Quality Review Completed | 2/4/2021 | CHIHARU SUZUKI |
| Building Plans Picked Up | 2/5/2021 | APPLICANT |
| Applicant returned to address corrections | 6/1/2021 | TARIK SAOUD |
| Plan Check Approved | 6/29/2021 | TARIK SAOUD |
| Issued | 7/2/2021 | APPLICANT |
| CofO in Progress | 8/18/2022 | OGANES TARAKHCHYAN |
| Permit Finaled | 8/26/2022 | DANIEL ORRANTE |
| CofO Issued | 8/26/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/26/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 3/5/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2021 | DINAH GARIN |
| Sewer availability | Cleared | 3/8/2021 | DINAH GARIN |
| Specific Plan | Cleared | 3/10/2021 | DYLAN SITTIG |
| Hydrant and Access approval | Cleared | 4/9/2021 | KURT CORRAL |
| Specific Plan | Cleared | 4/15/2021 | FREDDY GARCIA |
| Low Impact Development | Cleared | 4/21/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/29/2021 | DENNIS BRAGIN |
| Trees in Parkway | Cleared | 4/29/2021 | JOHN KIM |
| Frnt yard landscape/Water mgmt | Cleared | 5/14/2021 | LOUIS ORTEGA |
| Grading Pre-Inspection | Cleared | 6/29/2021 | TARIK SAOUD |
Contact Information
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/23/2021 | Partial Approval | KEVIN SARGSYAN |
| Sewer | 7/23/2021 | Approved | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 7/28/2021 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 7/28/2021 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/28/2021 | Approved | KEVIN SARGSYAN |
| METHANE-Barrier | 7/28/2021 | Approved | KEVIN SARGSYAN |
| METHANE-Subgrade | 7/28/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2021 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 10/28/2021 | No Result Entered | RONALD WEBER |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/29/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 11/29/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/14/2021 | Corrections Issued | KEVIN SARGSYAN |
| Shower Pan | 12/14/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/16/2021 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/11/2022 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 1/11/2022 | Corrections Issued | KEVIN SARGSYAN |
| METHANE-Rough | 1/11/2022 | Corrections Issued | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 1/11/2022 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/10/2022 | Partial Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 2/18/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 2/18/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Rough | 2/18/2022 | Approved | OGANES TARAKHCHYAN |
| Insulation | 3/24/2022 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 4/4/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 4/8/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 7/6/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 7/6/2022 | Corrections Issued | KEVIN SARGSYAN |
| Service/Power Release | 7/6/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Verify Rec and Parks Fee Memo | 7/6/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 7/11/2022 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 8/1/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 8/10/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 8/11/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 8/11/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/11/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/11/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 8/15/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 8/15/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/15/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 8/15/2022 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/15/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 8/17/2022 | OK to Issue CofO | OGANES TARAKHCHYAN |