10503 W ROUNTREE ROAD 90064

Certificate Information: 10503 W ROUNTREE ROAD 90064

Application / Permit
21010-30000-00328
Plan Check / Job No.
B21WL00286
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(n) 2-story SFD wih 2-car garage
Permit Issued
Issued on 7/2/2021
Issuing Office
Current Status
CofO Issued on 8/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2021 APPLICANT
Assigned to Plan Check Engineer 1/29/2021 TARIK SAOUD
Corrections Issued 2/1/2021 TARIK SAOUD
Quality Review Completed 2/4/2021 CHIHARU SUZUKI
Building Plans Picked Up 2/5/2021 APPLICANT
Applicant returned to address corrections 6/1/2021 TARIK SAOUD
Plan Check Approved 6/29/2021 TARIK SAOUD
Issued 7/2/2021 APPLICANT
CofO in Progress 8/18/2022 OGANES TARAKHCHYAN
Permit Finaled 8/26/2022 DANIEL ORRANTE
CofO Issued 8/26/2022 DANIEL ORRANTE
Permit Finaled 8/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 3/5/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 3/8/2021 DINAH GARIN
Sewer availability Cleared 3/8/2021 DINAH GARIN
Specific Plan Cleared 3/10/2021 DYLAN SITTIG
Hydrant and Access approval Cleared 4/9/2021 KURT CORRAL
Specific Plan Cleared 4/15/2021 FREDDY GARCIA
Low Impact Development Cleared 4/21/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/29/2021 DENNIS BRAGIN
Trees in Parkway Cleared 4/29/2021 JOHN KIM
Frnt yard landscape/Water mgmt Cleared 5/14/2021 LOUIS ORTEGA
Grading Pre-Inspection Cleared 6/29/2021 TARIK SAOUD

Contact Information

Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/23/2021 Partial Approval KEVIN SARGSYAN
Sewer 7/23/2021 Approved KEVIN SARGSYAN
Deputy Reinf. Concrete 7/28/2021 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 7/28/2021 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 7/28/2021 Approved KEVIN SARGSYAN
METHANE-Barrier 7/28/2021 Approved KEVIN SARGSYAN
METHANE-Subgrade 7/28/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 10/28/2021 No Result Entered RONALD WEBER
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/5/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 11/29/2021 Approved KEVIN SARGSYAN
HVAC-Rough 11/29/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 12/14/2021 Corrections Issued KEVIN SARGSYAN
Shower Pan 12/14/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 12/16/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/11/2022 Corrections Issued KEVIN SARGSYAN
Green Building Rough 1/11/2022 Corrections Issued KEVIN SARGSYAN
METHANE-Rough 1/11/2022 Corrections Issued KEVIN SARGSYAN
Verify Sprinkler Sign Off 1/11/2022 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/7/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 2/10/2022 Partial Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 2/18/2022 Approved OGANES TARAKHCHYAN
Green Building Rough 2/18/2022 Approved OGANES TARAKHCHYAN
METHANE-Rough 2/18/2022 Approved OGANES TARAKHCHYAN
Insulation 3/24/2022 Corrections Issued EVAN COOPER
Drywall Nailing 4/4/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 4/8/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 7/6/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Final 7/6/2022 Corrections Issued KEVIN SARGSYAN
Service/Power Release 7/6/2022 Not Ready for Inspection KEVIN SARGSYAN
Verify Rec and Parks Fee Memo 7/6/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 7/11/2022 Approved KEVIN SARGSYAN
HVAC-Final 8/1/2022 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 8/10/2022 Approved OGANES TARAKHCHYAN
Green Building Final 8/11/2022 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 8/11/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/11/2022 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 8/11/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Final 8/15/2022 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 8/15/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/15/2022 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 8/15/2022 Approved OGANES TARAKHCHYAN
Smoke Detectors 8/15/2022 Approved OGANES TARAKHCHYAN
Final 8/17/2022 OK to Issue CofO OGANES TARAKHCHYAN