10632 W MISSOURI AVE 90025

Certificate Information: 10632 W MISSOURI AVE 90025

Application / Permit
21010-30000-00222
Plan Check / Job No.
B21WL00219
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) two-story 1196 sq ft detached ADU per LAMC 12.22 A.33 (c) and (g)
Permit Issued
Issued on 11/3/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 FELIPE HERNANDEZ
Corrections Issued 2/2/2021 FELIPE HERNANDEZ
Quality Review Completed 2/8/2021 TARIK SAOUD
Applicant returned to address corrections 6/4/2021 FELIPE HERNANDEZ
Plan Check Approved 11/3/2021 FELIPE HERNANDEZ
Plan Check Approved 11/3/2021 FELIPE HERNANDEZ
Issued 11/3/2021 APPLICANT
Building Plans Picked Up 11/9/2021 APPLICANT
CofO in Progress 7/28/2023 STEPHANIE SWANSON
Permit Finaled 7/31/2023 DANIEL ORRANTE
CofO Issued 7/31/2023 DANIEL ORRANTE
Permit Finaled 7/31/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/23/2021 CATHERINE ADROVER
Permit Cleared 2/23/2021 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 2/25/2021 CATHERINE ADROVER
Sewer availability Cleared 2/26/2021 CATHERINE ADROVER
Specific Plan Cleared 3/3/2021 KEVIN ARUCAN
Hydrant and Access approval Cleared 4/23/2021 JOHN CONNEALLY
Grading Pre-Inspection Cleared 4/28/2021 BRIAN MILLER
Low Impact Development Cleared 5/16/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/20/2021 CATHERINE ADROVER

Contact Information

Contractor Aladdin Construction; Lic. No.: 677011-B 9740 LA CANADA WAY      SHADOW HILLS, CA 91040
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406
Engineer Yadegari,, Shahriar; Lic. No.: C64591 10301 KESWICK AVE      LOS ANGELES, CA 90064

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/6/2021 Approved KRISTEN CAUSEY
Footing/Foundation/Slab 12/22/2021 Corrections Issued BRENDAN LOONEY
METHANE-Barrier 12/22/2021 Not Ready for Inspection BRENDAN LOONEY
METHANE-Subgrade 12/22/2021 Not Ready for Inspection BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 3/21/2022 Approved BRENDAN LOONEY
Footing/Foundation/Slab 3/21/2022 Approved BRENDAN LOONEY
METHANE-Barrier 3/21/2022 Approved BRENDAN LOONEY
METHANE-Subgrade 3/21/2022 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 5/27/2022 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Corrections Issued STEPHANIE SWANSON
Gas Test 7/8/2022 Partial Approval EVAN COOPER
PLUMBING-Rough 7/8/2022 Approved EVAN COOPER
ELECTRICAL-Rough 7/21/2022 Corrections Issued PATRICK QUALEY
HVAC-Rough 7/21/2022 Approved PATRICK QUALEY
Interior/Exterior Lathing 7/21/2022 Approved PATRICK QUALEY
Green Building Rough 8/2/2022 Approved PATRICK QUALEY
METHANE-Rough 8/2/2022 Approved PATRICK QUALEY
Pre-Inspection 8/2/2022 Partial Inspection PATRICK QUALEY
Underground Mechanical 8/3/2022 Partial Approval PATRICK QUALEY
Insulation 8/10/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Insulation 8/15/2022 Approved ANDREW NAVE
Drywall Nailing 8/26/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 8/26/2022 Approved STEPHANIE SWANSON
Gas Test 8/26/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 8/26/2022 Partial Approval STEPHANIE SWANSON
Shower Pan 8/26/2022 Corrections Issued STEPHANIE SWANSON
Underground Mechanical 8/26/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 10/14/2022 Approved STEPHANIE SWANSON
Shower Pan 10/14/2022 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 4/7/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Final 4/7/2023 Corrections Issued STEPHANIE SWANSON
Final 4/7/2023 Corrections Issued STEPHANIE SWANSON
Green Building Final 4/7/2023 Approved STEPHANIE SWANSON
HVAC-Final 4/7/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 4/7/2023 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 4/7/2023 SGSOV Not Ready STEPHANIE SWANSON
Service/Power Release 4/7/2023 Not Ready for Inspection STEPHANIE SWANSON
Smoke Detectors 4/7/2023 Corrections Issued STEPHANIE SWANSON
Final 7/21/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 7/24/2023 Approved STEPHANIE SWANSON
Final 7/24/2023 Corrections Issued STEPHANIE SWANSON
HVAC-Final 7/24/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 7/24/2023 Approved STEPHANIE SWANSON
Service/Power Release 7/24/2023 Approved STEPHANIE SWANSON
Smoke Detectors 7/24/2023 Approved STEPHANIE SWANSON
Final 7/27/2023 OK to Issue CofO STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 7/27/2023 SGSOV Approved STEPHANIE SWANSON