734 N HENRY FORD AVE 90744

Certificate Information: 734 N HENRY FORD AVE 90744

Application / Permit
21010-30000-00185
Plan Check / Job No.
B21WL00177
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Storage Building
Work Description
(N) 12' X 20' X 10'- HIGH PRE-FABBED CONTAINER FOR EQUIPMENT ROOM AND STORAGE
Permit Issued
Issued on 5/16/2022
Issuing Office
Current Status
CofO Issued on 10/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 REZA HAGHIGHAT
Corrections Issued 3/10/2021 REZA HAGHIGHAT
Quality Review Completed 3/11/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/19/2022 REZA HAGHIGHAT
Plan Check Approved 2/24/2022 REZA HAGHIGHAT
Issued 5/16/2022 APPLICANT
Building Plans Picked Up 6/2/2022 APPLICANT
CofO in Progress 10/13/2022 JOEY BUCHANAN
Permit Finaled 10/17/2022 DAVID TSAU
CofO Issued 10/17/2022 DAVID TSAU
Permit Finaled 10/17/2022 DAVID TSAU

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/22/2021 CHINH DINH
Roof/Waste drainage to street Cleared 3/22/2021 CHINH DINH
Low Impact Development Cleared 5/12/2021 JORGE MEJIA LEMUS
Abandoned oil well Cleared 11/5/2021 JOHN CONNEALLY
Hydrant and Access approval Cleared 11/5/2021 JOHN CONNEALLY
Chemical processes Cleared 1/20/2022 SCAQMD APPROVED
Chemical processes Cleared 1/20/2022 SCAQMD APPROVED
Miscellaneous Cleared 1/20/2022 JOHN CONNEALLY
"Q" conditions Cleared 1/21/2022 NOAH MCCOY
Coastal Zone Cleared 1/21/2022 NOAH MCCOY
Miscellaneous Cleared 1/21/2022 NOAH MCCOY
ZA Case Cleared 1/21/2022 NOAH MCCOY
Green Code Cleared 2/3/2022 AARON COSTA
DAS Clearance Cleared 2/8/2022 REZA HAGHIGHAT

Contact Information

Contractor Arb Inc; Lic. No.: 194079-B 26000 COMMERCENTRE DR      LAKE FOREST, CA 92630
Engineer Milczewsky,, Juergen; Lic. No.: S2450 3275 EAST DATE ST      BREA, CA 92823
Engineer Surapaneni,, Rajeev; Lic. No.: S6114 1535 E 3350 S      SALT LAKE CITY, UT 84106

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/2/2022 Approved DAVID TSAU
Pre-Inspection 9/2/2022 Conditional Approval DAVID TSAU
Final 10/13/2022 Conditional Approval JOEY BUCHANAN
Footing/Foundation/Slab 10/13/2022 Approved JOEY BUCHANAN
Green Building Final 10/13/2022 Approved JOEY BUCHANAN
Green Building Rough 10/13/2022 Approved JOEY BUCHANAN
METHANE-Barrier 10/13/2022 Approved JOEY BUCHANAN
METHANE-Final 10/13/2022 Approved JOEY BUCHANAN
METHANE-Rough 10/13/2022 Approved JOEY BUCHANAN
METHANE-Subgrade 10/13/2022 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 10/13/2022 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 10/13/2022 Approved JOEY BUCHANAN
Verify Sprinkler Sign Off 10/13/2022 Approved JOEY BUCHANAN
Wood Frame 10/13/2022 Approved JOEY BUCHANAN