10101 W LOVELANE PL 90064

Certificate Information: 10101 W LOVELANE PL 90064

Application / Permit
21010-30000-00065
Plan Check / Job No.
B21WL00080
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-Story S.F.D w/Attached Garage
Permit Issued
Issued on 4/16/2021
Issuing Office
Current Status
CofO Issued on 7/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2021 APPLICANT
Assigned to Plan Check Engineer 1/20/2021 DAVID CASTILLO
Corrections Issued 2/2/2021 DAVID CASTILLO
Quality Review Completed 2/8/2021 TARIK SAOUD
Building Plans Picked Up 2/10/2021 APPLICANT
Applicant returned to address corrections 4/1/2021 DAVID CASTILLO
Plan Check Approved 4/13/2021 DAVID CASTILLO
Issued 4/16/2021 APPLICANT
CofO in Progress 7/6/2022 KEVIN SARGSYAN
Permit Finaled 7/7/2022 DANIEL ORRANTE
CofO Issued 7/7/2022 DANIEL ORRANTE
Permit Finaled 7/7/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 2/23/2021 WESTON PRINGLE
Hydrant and Access approval Cleared 3/3/2021 ROBERT DUFF
Eng Process Fee Ord 176,300 Cleared 3/10/2021 KATHLEEN LEE
Sewer availability Cleared 3/12/2021 KATHLEEN LEE
Low Impact Development Cleared 3/23/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/23/2021 KATHLEEN LEE
Grading Pre-Inspection Cleared 4/12/2021 DAVID CASTILLO

Contact Information

Contractor Owner-Builder       ,
Engineer Bains,, Gagan Prit Singh; Lic. No.: S4482 222 E HUNTINGTON DR STE 235      MONROVIA, CA 91016
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803
Landscape Architect Sparks,, Shelley E.; Lic. No.: LA2896 12224 ADDISON ST.      VALLEY VILLAGE, CA 91607

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/19/2021 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 5/19/2021 Partial Approval KEVIN SARGSYAN
Sewer 5/19/2021 Approved KEVIN SARGSYAN
Deputy Reinf. Concrete 6/3/2021 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 6/4/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/23/2021 Partial Approval JACK MATTILLO
Floor/Roof Diaphrgm/Shear Wall 8/2/2021 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 9/30/2021 Conditional Approval KEVIN SARGSYAN
PLUMBING-Rough 10/1/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 10/6/2021 Approved RYAN SALAZAR
ELECTRICAL-Rough 10/15/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/15/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 10/18/2021 Approved KEVIN SARGSYAN
HVAC-Rough 10/18/2021 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 10/19/2021 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 10/19/2021 Corrections Issued KEVIN SARGSYAN
Verify Sprinkler Sign Off 10/19/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 10/22/2021 Approved KEVIN SARGSYAN
Green Building Rough 10/22/2021 Approved KEVIN SARGSYAN
HVAC-Rough 10/22/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 10/22/2021 Partial Approval KEVIN SARGSYAN
Shower Pan 10/22/2021 Approved KEVIN SARGSYAN
Insulation 10/29/2021 Partial Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 10/29/2021 Approved STEPHANIE SWANSON
Insulation 11/2/2021 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 11/8/2021 Approved EVAN COOPER
Drywall Nailing 11/16/2021 Approved CLAYTON GRAHAM
ELECTRICAL-Final 6/29/2022 Corrections Issued KEVIN SARGSYAN
Gas Test 6/29/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 6/29/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 6/30/2022 Approved KEVIN SARGSYAN
Gas Test 6/30/2022 Approved KEVIN SARGSYAN
Green Building Final 6/30/2022 Approved KEVIN SARGSYAN
HVAC-Final 6/30/2022 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 6/30/2022 Approved KEVIN SARGSYAN
Smoke Detectors 6/30/2022 Approved KEVIN SARGSYAN
PLUMBING-Final 7/1/2022 Corrections Issued KEVIN SARGSYAN
Final 7/5/2022 OK to Issue CofO KEVIN SARGSYAN
HVAC-Final 7/5/2022 Approved KEVIN SARGSYAN
PLUMBING-Final 7/5/2022 Approved KEVIN SARGSYAN