10101 W LOVELANE PL 90064
Certificate Information: 10101 W LOVELANE PL 90064
- Application / Permit
- 21010-30000-00065
- Plan Check / Job No.
- B21WL00080
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-Story S.F.D w/Attached Garage
- Permit Issued
- Issued on 4/16/2021
- Issuing Office
- Current Status
- CofO Issued on 7/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2021 | DAVID CASTILLO |
| Corrections Issued | 2/2/2021 | DAVID CASTILLO |
| Quality Review Completed | 2/8/2021 | TARIK SAOUD |
| Building Plans Picked Up | 2/10/2021 | APPLICANT |
| Applicant returned to address corrections | 4/1/2021 | DAVID CASTILLO |
| Plan Check Approved | 4/13/2021 | DAVID CASTILLO |
| Issued | 4/16/2021 | APPLICANT |
| CofO in Progress | 7/6/2022 | KEVIN SARGSYAN |
| Permit Finaled | 7/7/2022 | DANIEL ORRANTE |
| CofO Issued | 7/7/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/7/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 2/23/2021 | WESTON PRINGLE |
| Hydrant and Access approval | Cleared | 3/3/2021 | ROBERT DUFF |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2021 | KATHLEEN LEE |
| Sewer availability | Cleared | 3/12/2021 | KATHLEEN LEE |
| Low Impact Development | Cleared | 3/23/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 3/23/2021 | KATHLEEN LEE |
| Grading Pre-Inspection | Cleared | 4/12/2021 | DAVID CASTILLO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bains,, Gagan Prit Singh; Lic. No.: S4482 | 222 E HUNTINGTON DR STE 235 MONROVIA, CA 91016 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
| Landscape Architect | Sparks,, Shelley E.; Lic. No.: LA2896 | 12224 ADDISON ST. VALLEY VILLAGE, CA 91607 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/19/2021 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/19/2021 | Partial Approval | KEVIN SARGSYAN |
| Sewer | 5/19/2021 | Approved | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 6/3/2021 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/4/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2021 | Partial Approval | JACK MATTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2021 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 9/30/2021 | Conditional Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/1/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/6/2021 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 10/15/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/18/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 10/18/2021 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/19/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 10/19/2021 | Corrections Issued | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 10/19/2021 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/22/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 10/22/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 10/22/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/22/2021 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 10/22/2021 | Approved | KEVIN SARGSYAN |
| Insulation | 10/29/2021 | Partial Inspection | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/29/2021 | Approved | STEPHANIE SWANSON |
| Insulation | 11/2/2021 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 11/8/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 11/16/2021 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 6/29/2022 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 6/29/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 6/29/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 6/30/2022 | Approved | KEVIN SARGSYAN |
| Gas Test | 6/30/2022 | Approved | KEVIN SARGSYAN |
| Green Building Final | 6/30/2022 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 6/30/2022 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 6/30/2022 | SGSOV Approved | KEVIN SARGSYAN |
| Service/Power Release | 6/30/2022 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 6/30/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 7/1/2022 | Corrections Issued | KEVIN SARGSYAN |
| Final | 7/5/2022 | OK to Issue CofO | KEVIN SARGSYAN |
| HVAC-Final | 7/5/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 7/5/2022 | Approved | KEVIN SARGSYAN |