7839-7841 N WILKINSON AVE 91605

Certificate Information: 7839-7841 N WILKINSON AVE 91605

Application / Permit
21010-20002-03219
Plan Check / Job No.
B22VN07122
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 1ST LEVEL GARAGE TO SB9 DWELLING UNIT. ADU AT 2ND FLOOR TO REMAIN.
Permit Issued
Issued on 9/6/2022
Issuing Office
Current Status
Permit Finaled on 2/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2022 APPLICANT
Assigned to Plan Check Engineer 6/16/2022 JOE VO
Corrections Issued 6/18/2022 JOE VO
Quality Review Completed 6/28/2022 GARO TELMI
Plan Check Approved 9/6/2022 JOE VO
Issued 9/6/2022 APPLICANT
Permit Finaled-Status Void 1/31/2023 MATTHEW NELSON
Permit Finaled 1/31/2023 MATTHEW NELSON
Re-Activate Permit 2/28/2023 MATTHEW NELSON

Permit Application Clearance Information

Address approval Cleared 7/11/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/11/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 7/11/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 8/5/2022 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: NA56881       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/25/2022 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Rough 10/25/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 10/25/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Sewer 10/25/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Wood Frame 10/25/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Drywall Nailing 11/18/2022 Partial Approval CHRISTOPHER DELLEFIELD
PLUMBING-Rough 11/18/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 11/28/2022 Approved MATTHEW NELSON
HVAC-Rough 11/28/2022 Approved MATTHEW NELSON
Insulation 11/28/2022 Approved MATTHEW NELSON
Wood Frame 11/28/2022 Approved MATTHEW NELSON
Shower Pan 12/5/2022 Approved MATTHEW NELSON
Drywall Nailing 12/9/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/9/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/31/2023 Approved MATTHEW NELSON
ELECTRICAL-Final 1/31/2023 Approved MATTHEW NELSON
Final 1/31/2023 Permit Finaled MATTHEW NELSON
Green Building Final 1/31/2023 Approved MATTHEW NELSON
Green Building Rough 1/31/2023 Approved MATTHEW NELSON
HVAC-Final 1/31/2023 Approved MATTHEW NELSON
MERV13>=Final 1/31/2023 Approved MATTHEW NELSON
MERV13>=Rough 1/31/2023 Approved MATTHEW NELSON
PLUMBING-Final 1/31/2023 Approved MATTHEW NELSON
Smoke Detectors 1/31/2023 Approved MATTHEW NELSON