6941-6943 N SIMPSON AVE 91605

Certificate Information: 6941-6943 N SIMPSON AVE 91605

Application / Permit
21010-20001-06267
Plan Check / Job No.
B23LA04918
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT (E) ATTACHED GARAGE AND STORAGE ROOM OF A DUPLEX TO AN ADU PER LAMC 12.22 A.33(c) AND (e) (REAR BLDG "B")
Permit Issued
Issued on 4/2/2025
Issuing Office
Current Status
CofO Issued on 3/17/2026
Certificate of Occupancy
282771 - CofO Issued More Information
282771 - CofO Issued More Information

Permit Application Status History

Submitted 3/21/2023 APPLICANT
Assigned to Plan Check Engineer 3/29/2023 SAM CHANG
Corrections Issued 4/25/2023 KHEDER ALRAZAA
Quality Review Completed 5/11/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 1/10/2024 SAM CHANG
Applicant returned to address corrections 1/2/2025 SAM CHANG
Applicant returned to address corrections 2/4/2025 SAM CHANG
Applicant returned to address corrections 3/19/2025 SAM CHANG
Plan Check Approved 3/28/2025 SAM CHANG
Issued 4/2/2025 APPLICANT
No Progress 2/11/2026 RAUL OLAGI
CofO in Progress 2/11/2026 RAUL OLAGI
CofO Issued 3/17/2026 RUBEN SALAS
Permit Finaled 3/17/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/27/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/6/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 12/6/2023 LEE GUILBEAUX
Miscellaneous Cleared 4/22/2024 MATHEW QUAN
DAS Clearance Cleared 1/30/2025 ELIZABETH TOMS
DAS Clearance Cleared 1/30/2025 ELIZABETH TOMS

Contact Information

Contractor Inhance Construction Inc; Lic. No.: 1073871-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/18/2025 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 4/18/2025 Partial Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 4/18/2025 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 4/18/2025 Partial Approval JAVIER RAMOS JR
Pre-Inspection 4/18/2025 Corrections Issued JAVIER RAMOS JR
Deputy Drilled-In Anchors 4/22/2025 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 5/2/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 5/22/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 6/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 6/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Wood Frame 6/9/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
Deputy Wood Construction 6/11/2025 Conditional Approval JOSE AVILA
ELECTRICAL-Rough 6/13/2025 Partial Approval JOSE AVILA
HVAC-Rough 6/13/2025 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 7/2/2025 Approved JOSE AVILA
ELECTRICAL-Rough 7/2/2025 Approved JOSE AVILA
HVAC-Rough 7/2/2025 Approved JOSE AVILA
Insulation 7/2/2025 Approved JOSE AVILA
PLUMBING-Rough 7/2/2025 Approved JOSE AVILA
Final 11/18/2025 Corrections Issued JOSE AVILA
Final 12/11/2025 Corrections Issued JOSE AVILA
Smoke Detectors 12/11/2025 Approved JOSE AVILA
Final 2/4/2026 Conditional Approval ROBERTO PALACIOS-LOPEZ