10165 W TOLUCA LAKE AVE 91602
Certificate Information: 10165 W TOLUCA LAKE AVE 91602
- Application / Permit
- 21010-20001-04370
- Plan Check / Job No.
- B23VN04776
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO 21010-20000-04370 TO MAKE REVISIONS TO PLANS, AREA AND ELEVATIONS, CHANGE ARCHITECT , ALL WORK PER ENGINEERING - SEE COMMENTS
- Permit Issued
- Issued on 11/28/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 5/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2023 | RARES BODEA |
| Corrections Issued | 4/24/2023 | RARES BODEA |
| Quality Review Completed | 4/27/2023 | STEVEN KIM |
| Building Plans Picked Up | 4/28/2023 | APPLICANT |
| Applicant returned to address corrections | 11/13/2023 | RARES BODEA |
| Plan Check Approved | 11/22/2023 | RARES BODEA |
| Issued | 11/28/2023 | APPLICANT |
| Permit Finaled | 5/27/2025 | JAVIER RAMOS JR |
Permit Application Clearance Information
| ZI | Cleared | 6/27/2023 | STEVEN WECHSLER |
| Low Impact Development (LID) | Cleared | 11/7/2023 | ERNEST TSE |
Contact Information
| Architect | Hamlet, Sadekyan; Lic. No.: C39815 | , |
| Contractor | A W I Builders Inc; Lic. No.: 818478-B | 1027 SHERLOCK DR BURBANK, CA 91501 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/2/2024 | Partial Approval | MANUEL TEJADA |
| Footing/Foundation/Slab | 1/25/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Masonry Wall/Backfill | 1/25/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Masonry Wall/Backfill | 1/29/2024 | Partial Approval | KIRK SANDERS |
| Reinforced Masonry Frame | 1/29/2024 | Partial Approval | KIRK SANDERS |
| Structural Steel Frame | 1/31/2024 | Not Ready for Inspection | KIRK SANDERS |
| Underground Mechanical | 1/31/2024 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 2/2/2024 | Approved | CRAIG DAVIS |
| Wood Frame | 2/29/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 12/4/2024 | Approved | CHRISTOPHER ROJAS |
| Sewer | 12/4/2024 | Approved | CHRISTOPHER ROJAS |