5233 N WOODLAKE AVE 91367
Certificate Information: 5233 N WOODLAKE AVE 91367
- Application / Permit
- 21010-20001-03686
- Plan Check / Job No.
- B22VN16572
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPP. TO PERMIT 21010-20000-03686 TO ADD 12'-9" x 18'-6" (NEW BEDROOM/BATHROOM) TO APPROVED IRR. SHAPED 27' x 28'-6" ONE-STORY DET. ACCESSORY DWELLING UNIT, RELOCATE EXIT DOOR, AND CHANGE THE ADU CODE TO BE PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 3/17/2023
- Issuing Office
- Current Status
- Permit Finaled on 11/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2022 | SEAN SHAHMIRI |
| Corrections Issued | 11/7/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 3/2/2023 | SEAN SHAHMIRI |
| Issued | 3/17/2023 | SHANNON HAAS |
| Permit Finaled | 11/4/2024 | GEVORK IPCHYAN |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/28/2022 | ANTHONY VARGAS |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2023 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 2/7/2023 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 2/7/2023 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 2/7/2023 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 2/7/2023 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 3/2/2023 | JOHN BACON |
| Hold | Cleared | 5/22/2023 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sayah,, Daniel H; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/12/2024 | Approved | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 3/4/2024 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 3/4/2024 | Approved | TROY SANDERS |
| PLUMBING-Rough | 3/4/2024 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 4/17/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2024 | Approved | GEVORK IPCHYAN |
| Green Building Final | 4/17/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| HVAC-Rough | 4/17/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Light Gage Steel Frame | 4/17/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Rough | 4/17/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Sewer | 4/17/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Shower Pan | 4/17/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 4/23/2024 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2024 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 4/23/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Rough | 4/23/2024 | Approved | GEVORK IPCHYAN |
| Sewer | 4/23/2024 | Approved | GEVORK IPCHYAN |
| Shower Pan | 4/23/2024 | Approved | GEVORK IPCHYAN |
| Underground Mechanical | 4/23/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 5/9/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 5/13/2024 | Partial Approval | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 5/20/2024 | Partial Approval | JOHN HAYES |
| Interior/Exterior Lathing | 6/7/2024 | Approved | GEVORK IPCHYAN |
| Insulation | 6/13/2024 | Approved | GEVORK IPCHYAN |
| Drywall Nailing | 6/21/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 6/26/2024 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 10/29/2024 | Approved | GEVORK IPCHYAN |
| Final | 10/29/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 10/29/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Rough | 10/29/2024 | Approved | GEVORK IPCHYAN |
| Smoke Detectors | 10/29/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Final | 11/4/2024 | Permit Finaled | GEVORK IPCHYAN |
| Green Building Final | 11/4/2024 | Approved | GEVORK IPCHYAN |
| Service/Power Release | 11/4/2024 | Approved | GEVORK IPCHYAN |
| Smoke Detectors | 11/4/2024 | Approved | GEVORK IPCHYAN |