12581 W BRANFORD ST 91331

Certificate Information: 12581 W BRANFORD ST 91331

Application / Permit
21010-20001-00347
Plan Check / Job No.
B22VN08254
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
SUPPL TO PERMIT # 21010-20000-00347, TO REVISE STRUCTURAL & FOUNDATION PLANS ALSO REPLACE CONVENTIONAL ROOF TO TRUSSES SYSTEM REVISE STRUCT INVENTORY & CHANGE ENGINEER OF RECORD.
Permit Issued
Issued on 6/28/2022
Issuing Office
Current Status
Permit Finaled on 6/18/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/26/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 TROY DEGUZMAN
Corrections Issued 6/3/2022 TROY DEGUZMAN
Quality Review Completed 6/8/2022 OMID HEDAYAT
Building Plans Picked Up 6/9/2022 APPLICANT
Plan Check Approved 6/28/2022 TROY DEGUZMAN
Issued 6/28/2022 APPLICANT
Permit Finaled 6/18/2025 GREGORY POMISH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/14/2022 Partial Approval BRUCE CAMPBELL
Footing/Foundation/Slab 7/19/2022 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 8/9/2022 Corrections Issued DANNY RODRIGUEZ
Masonry Wall/Backfill 8/11/2022 Not Ready for Inspection JOHN KITCKO
Masonry Wall/Backfill 8/15/2022 Conditional Approval JOHN KITCKO
Masonry Wall/Backfill 8/22/2022 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 8/23/2022 Corrections Issued DANNY RODRIGUEZ
Masonry Wall/Backfill 8/24/2022 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 9/1/2022 Partial Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 9/29/2022 Partial Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 10/26/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 10/27/2022 No Access for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 10/28/2022 Corrections Issued DANNY RODRIGUEZ
Masonry Wall/Backfill 10/31/2022 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 11/22/2022 No Access for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 3/9/2023 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 4/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 5/1/2023 Conditional Approval STEVEN LEVITT
Wood Frame 5/1/2023 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/3/2023 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 8/8/2023 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 8/25/2023 Not Ready for Inspection DANNY RODRIGUEZ