7745 N WISH AVE 91406
Certificate Information: 7745 N WISH AVE 91406
- Application / Permit
- 21010-20000-06942
- Plan Check / Job No.
- B21VN18156
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 32'-3" X 21' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d);
- Permit Issued
- Issued on 9/2/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | SELLA BENYAMIN |
| Corrections Issued | 1/19/2022 | SELLA BENYAMIN |
| Quality Review Completed | 1/21/2022 | STEVEN KIM |
| Building Plans Picked Up | 1/24/2022 | APPLICANT |
| Plan Check Approved | 8/4/2022 | SELLA BENYAMIN |
| Issued | 9/2/2022 | APPLICANT |
| CofO in Progress | 1/30/2023 | RAUL OLAGI |
| CofO Issued | 2/13/2023 | MICHAEL SMITH |
| Permit Finaled | 2/13/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/7/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/8/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 3/31/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 5/31/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 7/1/2022 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/26/2022 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 9/29/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2022 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2022 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 11/28/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 11/28/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 11/28/2022 | Not Ready for Inspection | RAUL OLAGI |
| Verify Sprinkler Sign Off | 11/28/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 12/5/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 12/5/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 12/5/2022 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 12/5/2022 | Approved | RAUL OLAGI |
| Insulation | 12/7/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 12/9/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 12/23/2022 | Approved | RAUL OLAGI |
| Sewer | 12/23/2022 | Approved | RAUL OLAGI |
| Underground Mechanical | 12/23/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 1/26/2023 | Approved | RAUL OLAGI |
| Final | 1/26/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 1/26/2023 | Approved | RAUL OLAGI |
| HVAC-Final | 1/26/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 1/26/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 1/26/2023 | Approved | RAUL OLAGI |
| Final | 1/30/2023 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 1/30/2023 | Approved | RAUL OLAGI |