4154 N LONGRIDGE AVE 91423
Certificate Information: 4154 N LONGRIDGE AVE 91423
- Application / Permit
- 21010-20000-06909
- Plan Check / Job No.
- B21VN18138
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 14'-2" x 84' ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 6/11/2024
- Issuing Office
- Current Status
- CofO Issued on 10/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | SELLA BENYAMIN |
| Corrections Issued | 2/3/2022 | SELLA BENYAMIN |
| Quality Review Completed | 2/8/2022 | STEVEN KIM |
| Building Plans Picked Up | 2/9/2022 | APPLICANT |
| Plan Check Approved | 4/9/2024 | SELLA BENYAMIN |
| Issued | 6/11/2024 | APPLICANT |
| CofO in Progress | 9/15/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 10/2/2025 | RUBEN SALAS |
| CofO Issued | 10/2/2025 | RUBEN SALAS |
| Permit Finaled | 10/2/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2022 | CARLOS AGUILERA |
| Permit | Cleared | 3/3/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/10/2022 | CARLOS AGUILERA |
| ZI | Cleared | 6/8/2023 | BRENNEN OBETO |
| Hydrant and Access approval | Cleared | 6/29/2023 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/24/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 10/31/2023 | COLIN LOREDO |
| Trees in Parkway | Cleared | 1/10/2024 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 4/9/2024 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 4/9/2024 | SELLA BENYAMIN |
Contact Information
| Contractor | B M R Enterprises; Lic. No.: 901546-B | 5250 LANKERSHIM BLVD STE 500 LOS ANGELES, CA 91601 |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/3/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Underground Mechanical | 7/3/2024 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 7/9/2024 | Approved | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 7/10/2024 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 9/6/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 9/12/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 9/13/2024 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 9/30/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/9/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 10/15/2024 | Partial Approval | DAVID MATSON |
| Green Building Rough | 10/15/2024 | Not Ready for Inspection | DAVID MATSON |
| Verify Sprinkler Sign Off | 10/15/2024 | Approved | DAVID MATSON |
| Wood Frame | 10/18/2024 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 10/28/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 11/4/2024 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 11/4/2024 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 11/13/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 8/14/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 8/14/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Final | 8/14/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 8/14/2025 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 8/14/2025 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 8/14/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 8/14/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 9/12/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 9/12/2025 | Approved | CHRISTOPHE COCHRAN |