7412 N LASAINE AVE 91406

Certificate Information: 7412 N LASAINE AVE 91406

Application / Permit
21010-20000-06888
Plan Check / Job No.
B21VN18127
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (39'-0"x 23'-01") IRR SHAPE TWO STORY ACCESSORY DWELLING UNIT WITH ATT 2-CAR GARAGE PER LAMC 12.22 A.33 (c) and (d). WORK PER ENGINEER.
Permit Issued
Issued on 6/27/2022
Issuing Office
Current Status
CofO Issued on 6/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 TROY DEGUZMAN
Corrections Issued 2/22/2022 TROY DEGUZMAN
Quality Review Completed 2/28/2022 OMID HEDAYAT
Building Plans Picked Up 3/2/2022 APPLICANT
Plan Check Approved 6/27/2022 TROY DEGUZMAN
Issued 6/27/2022 APPLICANT
CofO in Progress 5/30/2023 RAUL OLAGI
CofO Issued 6/5/2023 MICHAEL SMITH
Permit Finaled 6/5/2023 MICHAEL SMITH

Permit Application Clearance Information

Hold Cleared 2/21/2022 JASON SHEETS
Address approval Cleared 3/2/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/2/2022 LEE GUILBEAUX
Hydrant and Access approval Cleared 4/1/2022 CINDY JOSSELYN
Construction near power lines Cleared 4/19/2022 RIDWAN HARDY
Low Impact Development Cleared 5/3/2022 KHAING AYE
Roof/Waste drainage to street Cleared 5/4/2022 LEE GUILBEAUX
Sewer availability Cleared 6/3/2022 ABDULLAH SADOZAI
Green Code Cleared 6/27/2022 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/17/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 8/29/2022 Partial Approval RAUL OLAGI
Sewer 8/29/2022 Approved RAUL OLAGI
Footing/Foundation/Slab 9/15/2022 Approved RAUL OLAGI
Deputy Reinf. Concrete 9/20/2022 Conditional Approval ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 9/28/2022 Partial Approval RAUL OLAGI
PLUMBING-Rough 9/28/2022 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 10/4/2022 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Corrections Issued RAUL OLAGI
Deputy Wood Construction 10/17/2022 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 10/25/2022 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 10/25/2022 Approved RAUL OLAGI
Deputy Wood Construction 10/26/2022 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 11/14/2022 Approved RAUL OLAGI
ELECTRICAL-Rough 11/14/2022 Approved RAUL OLAGI
Green Building Rough 11/14/2022 Approved RAUL OLAGI
HVAC-Rough 11/14/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 11/14/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 11/14/2022 Approved RAUL OLAGI
Underground Mechanical 11/14/2022 Approved RAUL OLAGI
Verify Sprinkler Sign Off 11/14/2022 Approved RAUL OLAGI
Insulation 11/30/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 11/30/2022 Partial Approval RAUL OLAGI
Drywall Nailing 12/12/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 12/12/2022 Not Ready for Inspection RAUL OLAGI
Interior/Exterior Lathing 12/19/2022 Approved RAUL OLAGI
ELECTRICAL-Final 3/21/2023 Corrections Issued RAUL OLAGI
Final 3/21/2023 Corrections Issued RAUL OLAGI
HVAC-Final 3/21/2023 Corrections Issued RAUL OLAGI
PLUMBING-Final 3/21/2023 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 3/21/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 3/21/2023 Approved RAUL OLAGI
ELECTRICAL-Final 5/9/2023 Approved RAUL OLAGI
Final 5/9/2023 Corrections Issued RAUL OLAGI
Green Building Final 5/9/2023 Approved RAUL OLAGI
HVAC-Final 5/9/2023 Approved RAUL OLAGI
PLUMBING-Final 5/9/2023 Approved RAUL OLAGI
Final 5/30/2023 OK to Issue CofO RAUL OLAGI
Service/Power Release 5/30/2023 Approved RAUL OLAGI