13826 W CALIFA ST 91401

Certificate Information: 13826 W CALIFA ST 91401

Application / Permit
21010-20000-06846
Plan Check / Job No.
B21VN18105
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING WITH 2-CAR ATTACHED GARAGE WITH ATTACHED TRELLIS AT REAR OF BUILDING.
Permit Issued
Issued on 4/20/2022
Issuing Office
Current Status
CofO Issued on 6/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2021 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 PRANITA SHAH
Corrections Issued 2/9/2022 PRANITA SHAH
Quality Review Completed 2/16/2022 KEN GILL
Applicant returned to address corrections 3/18/2022 PRANITA SHAH
Plan Check Approved 4/15/2022 PRANITA SHAH
Plan Check Approved 4/20/2022 PRANITA SHAH
Issued 4/20/2022 APPLICANT
Building Plans Picked Up 4/22/2022 APPLICANT
CofO in Progress 6/1/2023 RYAN SALAZAR
Permit Finaled 6/13/2023 MICHAEL SMITH
CofO Issued 6/13/2023 MICHAEL SMITH
Permit Finaled 6/13/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/23/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/23/2022 CARLOS AGUILERA
Permit Cleared 2/23/2022 CARLOS AGUILERA
Sewer availability Cleared 2/23/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 2/25/2022 LAURINDA MEADE
Low Impact Development Cleared 3/7/2022 TA ANH
Roof/Waste drainage to street Cleared 3/10/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/25/2022 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 4/27/2022 Partial Approval RICHARD DOCKUS
Footing/Foundation/Slab 5/5/2022 Corrections Issued RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 5/6/2022 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 5/7/2022 Off-Hour Fees Due
Footing/Foundation/Slab 5/9/2022 Approved RICHARD DOCKUS
Deputy Drilled-In Anchors 7/19/2022 Conditional Approval MATT KELLERMAN
BUILDING-Rough-Frame 9/14/2022 Corrections Issued RICHARD DOCKUS
Sewer 9/14/2022 Approved RICHARD DOCKUS
Deputy Wood Construction 9/16/2022 Conditional Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 9/19/2022 Partial Approval RICHARD DOCKUS
Sewer 9/19/2022 Approved RICHARD DOCKUS
Wood Frame 9/19/2022 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 9/22/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 9/22/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 9/27/2022 Corrections Issued DEANDRE HOFFMAN
Green Building Rough 9/27/2022 Not Ready for Inspection DEANDRE HOFFMAN
HVAC-Rough 9/27/2022 Approved DEANDRE HOFFMAN
Verify Sprinkler Sign Off 9/27/2022 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 9/28/2022 Corrections Issued CALEB MEISTER
Insulation 10/5/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/5/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/19/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Drywall Nailing 10/19/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 10/19/2022 Approved CHRISTOPHER DELLEFIELD
Service/Power Release 10/19/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Shower Pan 10/19/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 10/21/2022 Approved JENNIFER RABUCHIN
Shower Pan 10/21/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/27/2022 Approved RICHARD DOCKUS
Service/Power Release 12/1/2022 Not Ready for Inspection JOHN COLEMAN
ELECTRICAL-Final 5/17/2023 Corrections Issued ROBERT GOLD
Final 5/17/2023 Corrections Issued ROBERT GOLD
Green Building Final 5/17/2023 Not Ready for Inspection ROBERT GOLD
HVAC-Final 5/17/2023 Corrections Issued ROBERT GOLD
PLUMBING-Final 5/17/2023 Corrections Issued ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 5/17/2023 SGSOV Not Ready ROBERT GOLD
Service/Power Release 5/17/2023 Not Ready for Inspection ROBERT GOLD
Smoke Detectors 5/17/2023 Approved ROBERT GOLD
ELECTRICAL-Final 5/31/2023 Approved RYAN SALAZAR
Final 5/31/2023 OK to Issue CofO RYAN SALAZAR
Gas Test 5/31/2023 Approved RYAN SALAZAR
Green Building Final 5/31/2023 Approved RYAN SALAZAR
HVAC-Final 5/31/2023 Approved RYAN SALAZAR
PLUMBING-Final 5/31/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/31/2023 SGSOV Approved RYAN SALAZAR
Service/Power Release 5/31/2023 Approved RYAN SALAZAR