1039 E 28TH ST 1-20 90011

Certificate Information: 1039 E 28TH ST 1-20 90011

Application / Permit
21010-20000-06753
Plan Check / Job No.
B21VN18004
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3 STORY 20 UNITS (100% AFFORDABLE HOUSING PROJECT WITH 3 EXTREMELY LOW UNITS AND 17 LOW INCOME UNITS) APARTMENT TO INCLUDE 3 STORY TYPE VA APARTMENT USING TIER 3 TOC
Permit Issued
Issued on 2/10/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2021 APPLICANT
Assigned to Plan Check Engineer 1/6/2022 VU NGUYEN
Disabled Access Plans Picked Up 1/6/2022 APPLICANT
Corrections Issued 1/24/2022 VU NGUYEN
Quality Review Completed 1/27/2022 EUGENE BARBEAU
Applicant returned to address corrections 4/7/2022 VU NGUYEN
Building Plans Picked Up 4/12/2022 APPLICANT
Applicant returned to address corrections 11/3/2022 VU NGUYEN
Plan Check Approved 12/5/2022 VU NGUYEN
Issued 2/10/2023 APPLICANT
CofO in Progress 2/24/2025 JAMES POWERS
Permit Finaled 2/24/2025 RAFAEL ESPINOZA
CofO Issued 2/24/2025 RAFAEL ESPINOZA
Permit Finaled 2/24/2025 RAFAEL ESPINOZA

Permit Application Clearance Information

CPC Cleared 2/4/2022 LAMBERT GIESSINGER
Address approval Cleared 2/8/2022 CINDY QI
Community Plan Implem. Overlay Cleared 2/8/2022 CINDY QI
Highway dedication Cleared 2/8/2022 CINDY QI
Permit Cleared 2/8/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 2/9/2022 CINDY QI
Sewer availability Cleared 2/14/2022 CINDY QI
Miscellaneous Cleared 4/4/2022 DALIA MOKAYED
Building over 36-ft Cleared 5/4/2022 CALOSHA APPROVED
Hydrant and Access approval Cleared 5/6/2022 JOHN CONNEALLY
Frnt yard landscape/Water mgmt Cleared 5/9/2022 DALIA MOKAYED
Opn space landscape/Water mgmt Cleared 5/9/2022 DALIA MOKAYED
Green Code Cleared 5/16/2022 AARON COSTA
Low Impact Development Cleared 7/29/2022 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 8/2/2022 CINDY QI
DAS Clearance Cleared 8/4/2022 Rodolfo Arias
Fire Marshal Fire Life Safety Cleared 8/11/2022 RONILO MULAWIN
Community Plan Implem. Overlay Cleared 9/7/2022 HELEN JADALI
Historic Resource Verification Cleared 9/15/2022 MAX LODER
Redevelopment Project Area Cleared 9/20/2022 GRACIELA ACOSTA
Density Bonus 12.22.A.31 Cleared 11/29/2022 DORIS KWOK
SB8 RUD Cleared 11/29/2022 DORIS KWOK

Contact Information

Contractor Owner-Builder       ,
Engineer Bozorgnia,, Behrouz; Lic. No.: C79581 1557 WESTWOOD BLVD 145      LOS ANGELES, CA 90024
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 123 N VALENCIA ST      ALHAMBRA, CA 91801

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/19/2023 Approved RAFAEL ESPINOZA
Deputy Other (see comments) 4/27/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 4/27/2023 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 4/28/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/11/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 5/11/2023 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 5/11/2023 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 5/12/2023 Conditional Approval MICHAEL ROSENBERG
Pre-Inspection 5/12/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 6/1/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 6/1/2023 Partial Approval LARRY ARNICK
Green Building Rough 6/1/2023 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 6/1/2023 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 6/9/2023 Partial Approval JAMES POWERS
Insulation 6/9/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 6/13/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 6/21/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 6/22/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 7/7/2023 Partial Approval JAMES POWERS
Green Building Rough 8/9/2023 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/9/2023 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 8/9/2023 Partial Inspection RAFAEL ESPINOZA
Green Building Rough 9/12/2023 Approved JAMES POWERS
Verify Sprinkler Sign Off 9/12/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 9/12/2023 Partial Approval JAMES POWERS
Special/Order Compliance 10/13/2023 Partial Inspection NICK DANERI
Drywall Nailing 10/19/2023 Partial Approval RAFAEL ESPINOZA
Insulation 10/19/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Partial Approval RAFAEL ESPINOZA
Insulation 11/6/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/9/2023 Partial Approval JAMES POWERS
Insulation 11/21/2023 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 11/27/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 11/27/2023 Partial Approval JAMES POWERS
Insulation 12/14/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 1/17/2024 Partial Approval JAMES POWERS
Drywall Nailing 1/30/2024 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 3/7/2024 Approved JAMES POWERS
Drywall Nailing 4/4/2024 Partial Approval JAMES POWERS
Drywall Nailing 4/11/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 5/8/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 5/15/2024 Not Ready for Inspection JAMES POWERS
Final 1/22/2025 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 1/22/2025 Approved JAMES POWERS
Green Building Final 1/22/2025 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 1/22/2025 SGSOV Approved JAMES POWERS
Smoke Detectors 1/22/2025 Approved JAMES POWERS
Verify Sprinkler Sign Off 1/22/2025 Approved JAMES POWERS
Wood Frame 1/22/2025 Approved JAMES POWERS
Final 1/30/2025 OK for TCO JAMES POWERS
Final 2/7/2025 OK for TCO JAMES POWERS
Final 2/14/2025 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 2/24/2025 Partial Approval JAMES POWERS
Deputy Wood Construction 2/24/2025 Partial Approval JAMES POWERS
Final 2/24/2025 OK to Issue CofO JAMES POWERS