11310 W MARTHA ST 91601

Certificate Information: 11310 W MARTHA ST 91601

Application / Permit
21010-20000-06746
Plan Check / Job No.
B21VN17974
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY (30'-0"x20'-0"), 1200 SQFT DETACHED ADU W/NFPA 13D SPRINKLERS THROUGHOUT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 2/15/2023
Issuing Office
Metro
Current Status
CofO Issued on 1/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2022 PETER MOSESIAN
Corrections Issued 1/23/2022 PETER MOSESIAN
Quality Review Completed 1/27/2022 OMID HEDAYAT
Building Plans Picked Up 1/31/2022 APPLICANT
Plan Check Approved 2/2/2023 PETER MOSESIAN
Issued 2/15/2023 APPLICANT
CofO in Progress 1/6/2025 JOSE AVILA
Permit Finaled 1/17/2025 RUBEN SALAS
CofO Issued 1/17/2025 RUBEN SALAS
Permit Finaled 1/17/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/28/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 2/1/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 2/1/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 8/22/2022 GILBERT URREA
Low Impact Development Cleared 12/13/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 12/14/2022 CARLOS AGUILERA
Hold Cleared 3/6/2023 MARIA VENDIVIL

Contact Information

Contractor Cswf Construction Inc; Lic. No.: 1021458-B 15831 SAN JOSE AVE      LA PUENETE, CA 91744
Engineer Desai,, Anil T; Lic. No.: C24653 1530 VIA LOS COYOTES      LA HABRA, CA 90631
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274
Engineer Salehipour,, Sassan Abolghasem; Lic. No.: C44172 1290 NORTH LAKE AVENUE STE 204      PASADENA, CA 91104

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/31/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 5/31/2023 Corrections Issued JOHN HAYES
Underground Mechanical 6/8/2023 Approved JOHN HAYES
Footing/Foundation/Slab 6/21/2023 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Partial Approval DAVID ANDERSON
Deputy Wood Construction 8/22/2023 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 9/1/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 9/7/2023 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Corrections Issued JOHN HAYES
HVAC-Rough 9/7/2023 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Partial Approval JOHN HAYES
Special/Order Compliance 9/12/2023 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Partial Approval JOHN HAYES
ELECTRICAL-Rough 9/28/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 9/28/2023 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 9/28/2023 Partial Approval JOHN HAYES
PLUMBING-Rough 9/28/2023 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 10/6/2023 Corrections Issued JOHN HAYES
HVAC-Rough 10/6/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 10/6/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 10/16/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 10/16/2023 Not Ready for Inspection JOHN HAYES
Green Building Rough 10/16/2023 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 10/16/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 10/23/2023 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 10/25/2023 Not Ready for Inspection ROBERT GOLD
ELECTRICAL-Rough 10/25/2023 Not Ready for Inspection ROBERT GOLD
Green Building Rough 10/25/2023 Approved ROBERT GOLD
HVAC-Rough 10/25/2023 Corrections Issued ROBERT GOLD
PLUMBING-Rough 10/25/2023 Approved ROBERT GOLD
Verify Sprinkler Sign Off 10/25/2023 Approved ROBERT GOLD
ELECTRICAL-Rough 11/3/2023 Approved CHRISTOPHE COCHRAN
HVAC-Rough 11/7/2023 Approved CHRISTOPHER ROJAS
Wood Frame 11/7/2023 Approved CHRISTOPHER ROJAS
Insulation 11/16/2023 Approved JOHN HAYES
Drywall Nailing 11/20/2023 Approved ROBERT GOLD
Interior/Exterior Lathing 11/21/2023 Approved JOHN COLEMAN
PLUMBING-Rough 2/22/2024 Not Ready for Inspection JOHN HAYES
Sewer 2/22/2024 Not Ready for Inspection JOHN HAYES
Underground Mechanical 2/22/2024 Corrections Issued JOHN HAYES
Sewer 3/22/2024 Approved JOHN HAYES
Underground Mechanical 3/22/2024 Approved JOHN HAYES
ELECTRICAL-Final 10/10/2024 Corrections Issued JOSE AVILA
PLUMBING-Final 10/10/2024 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 10/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 10/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 10/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 10/18/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 10/18/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 10/18/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 10/18/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 10/28/2024 Approved JOSE AVILA
Gas Test 10/28/2024 Approved JOSE AVILA
PLUMBING-Final 10/28/2024 Approved JOSE AVILA
Service/Power Release 11/18/2024 Approved JOSE AVILA
Final 12/6/2024 Corrections Issued JOSE AVILA
Final 12/12/2024 Not Ready for Inspection JOSE AVILA
Final 1/6/2025 OK to Issue CofO JOSE AVILA