15142 W LA MAIDA ST 91403
Certificate Information: 15142 W LA MAIDA ST 91403
- Application / Permit
- 21010-20000-06744
- Plan Check / Job No.
- B21VN17972
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 21'3" X 33'4" TWO STORY ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33 (C) AND (D) WITH 9'9" X 21'3" PATIO COVER, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING- SEE COMMENTS
- Permit Issued
- Issued on 3/19/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2022 | RARES BODEA |
| Corrections Issued | 2/10/2022 | RARES BODEA |
| Quality Review Completed | 2/17/2022 | STEVEN KIM |
| Building Plans Picked Up | 2/23/2022 | APPLICANT |
| Plan Check Approved | 10/3/2023 | RARES BODEA |
| Issued | 3/19/2024 | APPLICANT |
| CofO in Progress | 6/3/2025 | JACK KARGODORIAN |
| Permit Finaled | 3/5/2026 | RUBEN SALAS |
| CofO Issued | 3/5/2026 | RUBEN SALAS |
| Permit Finaled | 3/5/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/30/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/5/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 7/11/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/9/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | All Star Fence And Concrete; Lic. No.: 511400-B | P O BOX 221771 NEWHALL, CA 913221771 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/12/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Underground Mechanical | 6/12/2024 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 6/14/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2024 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2024 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 8/16/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 8/16/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Sewer | 8/16/2024 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 8/22/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 8/22/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 9/20/2024 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 9/20/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 9/20/2024 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 9/20/2024 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 9/20/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 9/20/2024 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 9/20/2024 | Approved | JACK KARGODORIAN |
| Special/Order Compliance | 9/23/2024 | Partial Inspection | DAVID MATSON |
| Interior/Exterior Lathing | 10/7/2024 | Partial Approval | MISAEL ESPARZA |
| Insulation | 10/11/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 10/18/2024 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/23/2024 | Approved | JACK KARGODORIAN |
| Insulation | 10/23/2024 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 10/31/2024 | Approved | JACK KARGODORIAN |
| Shower Pan | 11/19/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 11/25/2024 | Approved | VINCENT HANLEY |
| Gas Test | 3/3/2025 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 3/3/2025 | Approved | JACK KARGODORIAN |
| Final | 4/18/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 4/18/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| MERV13>=Final | 4/18/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 4/18/2025 | SGSOV Not Ready | JACK KARGODORIAN |
| Service/Power Release | 4/18/2025 | Corrections Issued | JACK KARGODORIAN |
| Smoke Detectors | 4/18/2025 | Approved | JACK KARGODORIAN |
| Final | 6/2/2025 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 6/2/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/2/2025 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 6/2/2025 | Approved | JACK KARGODORIAN |