2533-2535 S CURSON AVE 90016

Certificate Information: 2533-2535 S CURSON AVE 90016

Application / Permit
21010-20000-06740
Plan Check / Job No.
B21VN17961
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 4-STORY 29'-7 3/16" x 89'-0 1/4" DUPLEX W/ ATT. 4-CAR GARAGE; NFPA-13R SPRINKLER SYSTEM THROUGHOUT
Permit Issued
Issued on 8/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 SEAN SHAHMIRI
Corrections Issued 2/3/2022 SEAN SHAHMIRI
Quality Review Completed 2/4/2022 OMID HEDAYAT
Building Plans Picked Up 2/7/2022 APPLICANT
Applicant returned to address corrections 2/14/2022 SEAN SHAHMIRI
Applicant returned to address corrections 4/29/2022 SEAN SHAHMIRI
Applicant returned to address corrections 5/23/2022 SEAN SHAHMIRI
Plan Check Approved 5/23/2022 SEAN SHAHMIRI
Issued 8/29/2022 APPLICANT
CofO in Progress 7/1/2024 JOAQUIN GREENOUGH
Permit Finaled 9/6/2024 RUBEN SALAS
CofO Issued 9/6/2024 RUBEN SALAS
Permit Finaled 9/6/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/14/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/17/2022 WALLIE JONG
Sewer availability Cleared 4/5/2022 WALLIE JONG
Hydrant and Access approval Cleared 4/8/2022 KURT CORRAL
Low Impact Development Cleared 4/26/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 4/26/2022 WALLIE JONG
Building over 36-ft Cleared 5/23/2022 CALOSHA APPROVED

Contact Information

Architect Chun,, Youngmin; Lic. No.: C32890 1828 LINCOLN BLVD #B      SANTA MONICA, CA 90404
Contractor Cohaus Llc; Lic. No.: 1083865-B 701 S SAN GABRIEL BLVD STE D      SAN GABRIEL, CA 91776
Engineer Lee,, Jack C; Lic. No.: GE2153 576 E LAMBERT RD      BREA, CA 92821
Engineer Lin,, Jason K; Lic. No.: S6095 1529 W LONGHILL DR      MONTEREY PARK, CA 91754

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/24/2023 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 4/10/2023 Partial Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 4/14/2023 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/14/2023 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 4/21/2023 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 4/21/2023 Partial Approval RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 4/25/2023 Approved JOSE AVILA
Deputy Reinf. Concrete 4/26/2023 Conditional Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 5/10/2023 Not Ready for Inspection JOSE AVILA
Footing/Foundation/Slab 5/12/2023 Corrections Issued JOSE AVILA
Deputy Drilled-In Anchors 5/16/2023 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 5/16/2023 Approved JOSE AVILA
Deputy Reinf. Concrete 5/17/2023 Conditional Approval JOSE AVILA
Deputy Steel/Welding 6/13/2023 Approved DONALD CRICHLOW
Deputy Steel/Welding 6/14/2023 Approved DONALD CRICHLOW
Wood Frame 7/6/2023 Conditional Approval JOSE AVILA
Deputy Wood Construction 7/28/2023 Approved DONALD CRICHLOW
Floor/Roof Diaphrgm/Shear Wall 7/31/2023 Corrections Issued JOSE AVILA
Deputy Wood Construction 8/11/2023 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/14/2023 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/31/2023 Approved JOSE AVILA
Deputy Wood Construction 9/18/2023 Conditional Approval JOSE AVILA
Wood Frame 9/21/2023 Corrections Issued JOSE AVILA
Wood Frame 10/16/2023 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 No Access for Inspection RONNIE MINDANAO
HVAC-Rough 11/2/2023 No Access for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 11/7/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 11/15/2023 Approved JOSE AVILA
HVAC-Rough 11/15/2023 Approved JOSE AVILA
PLUMBING-Rough 11/15/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 11/16/2023 Partial Approval JUSTIN HAWLEY
ELECTRICAL-Rough 11/16/2023 Approved JUSTIN HAWLEY
Insulation 11/16/2023 Not Ready for Inspection JUSTIN HAWLEY
PLUMBING-Rough 11/16/2023 Approved JUSTIN HAWLEY
Insulation 11/27/2023 Not Ready for Inspection RICHARD DOCKUS
Wood Frame 11/27/2023 Not Ready for Inspection RICHARD DOCKUS
Insulation 11/29/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 11/29/2023 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 12/6/2023 Partial Inspection RONNIE MINDANAO
BUILDING-Rough-Frame 12/8/2023 Partial Approval STUART CHAPMAN
Interior/Exterior Lathing 12/8/2023 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 12/13/2023 Corrections Issued RONNIE MINDANAO
Drywall Nailing 1/3/2024 Approved JOSH MEISTER
Green Building Rough 1/3/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 1/3/2024 Partial Approval JOSH MEISTER
BUILDING-Rough-Frame 3/20/2024 Partial Approval STUART CHAPMAN
Final 3/20/2024 Partial Inspection STUART CHAPMAN
Green Building Final 3/20/2024 Not Ready for Inspection STUART CHAPMAN
MERV13>=Final 3/20/2024 Not Ready for Inspection STUART CHAPMAN
MERV13>=Rough 3/20/2024 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/20/2024 SGSOV Not Ready STUART CHAPMAN
Service/Power Release 3/20/2024 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 3/20/2024 Not Ready for Inspection STUART CHAPMAN
Underground Mechanical 3/20/2024 Partial Approval STUART CHAPMAN
Verify Sprinkler Sign Off 3/20/2024 Approved STUART CHAPMAN
Sewer 3/28/2024 Approved STUART CHAPMAN
BUILDING-Rough-Frame 5/22/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Final 5/22/2024 Corrections Issued ARTHUR NEGRETE
Final 5/22/2024 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 5/22/2024 Corrections Issued ARTHUR NEGRETE
HVAC-Final 5/22/2024 Corrections Issued ARTHUR NEGRETE
MERV13>=Final 5/22/2024 Not Ready for Inspection ARTHUR NEGRETE
PLUMBING-Final 5/22/2024 Corrections Issued ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 5/22/2024 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 5/22/2024 Not Ready for Inspection ARTHUR NEGRETE
Smoke Detectors 5/22/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Final 5/29/2024 Corrections Issued AMIR NAZARIAN
HVAC-Final 5/29/2024 Approved AMIR NAZARIAN
PLUMBING-Final 5/29/2024 Approved AMIR NAZARIAN
Service/Power Release 5/29/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Final 6/5/2024 Approved ARTHUR NEGRETE
HVAC-Final 6/5/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 6/5/2024 Approved ARTHUR NEGRETE
Service/Power Release 6/5/2024 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Final 6/6/2024 Approved ENRIQUE MIRELES
Final 6/6/2024 Corrections Issued ENRIQUE MIRELES
Green Building Final 6/6/2024 Approved ENRIQUE MIRELES
HVAC-Final 6/6/2024 Approved ENRIQUE MIRELES
MERV13>=Final 6/6/2024 Approved ENRIQUE MIRELES
PLUMBING-Final 6/6/2024 Approved ENRIQUE MIRELES
Service/Power Release 6/11/2024 Approved ARTHUR NEGRETE
Final 6/28/2024 OK to Issue CofO ARTHUR NEGRETE
Special/Order Compliance 7/23/2024 Corrections Issued ARTHUR NEGRETE