4519 N BECK AVE 91602

Certificate Information: 4519 N BECK AVE 91602

Application / Permit
21010-20000-06739
Plan Check / Job No.
B21VN17954
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ADU PER CA Govt. Code 65852.2(e)(1)(B) and LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 9/12/2022
Issuing Office
Valley
Current Status
Issued on 9/12/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/29/2021 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 KHEDER ALRAZAA
Corrections Issued 2/10/2022 KHEDER ALRAZAA
Quality Review Completed 2/18/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 2/23/2022 APPLICANT
Plan Check Approved 9/8/2022 KHEDER ALRAZAA
Issued 9/12/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/24/2022 CARLOS AGUILERA
Permit Cleared 2/24/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/25/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 3/28/2022 CINDY JOSSELYN
Sewer availability Cleared 5/26/2022 CARLOS AGUILERA
ZI Cleared 6/13/2022 DANG NGUYEN
Low Impact Development Cleared 8/23/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 9/12/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/16/2022 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 9/21/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 9/26/2022 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 9/29/2022 Approved MISAEL ESPARZA
HVAC-Rough 1/18/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 1/18/2023 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 1/24/2023 Approved JACK KARGODORIAN
ELECTRICAL-Rough 1/24/2023 Approved JACK KARGODORIAN
Green Building Rough 1/24/2023 Approved JACK KARGODORIAN
MERV13>=Rough 1/24/2023 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 1/24/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 1/31/2023 Partial Approval JACK KARGODORIAN
Insulation 2/13/2023 Approved JACK KARGODORIAN
Shower Pan 2/13/2023 Not Ready for Inspection JACK KARGODORIAN
Drywall Nailing 2/21/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 2/28/2023 Partial Approval JACK KARGODORIAN
ELECTRICAL-Final 9/1/2023 Approved JACK KARGODORIAN
HVAC-Final 9/1/2023 Approved JACK KARGODORIAN
PLUMBING-Final 9/1/2023 Approved JACK KARGODORIAN