4521 N BECK AVE 91602
Certificate Information: 4521 N BECK AVE 91602
- Application / Permit
- 21010-20000-06738
- Plan Check / Job No.
- B21VN17954
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 9/12/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | KHEDER ALRAZAA |
| Corrections Issued | 2/10/2022 | KHEDER ALRAZAA |
| Quality Review Completed | 2/18/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 2/23/2022 | APPLICANT |
| Plan Check Approved | 9/8/2022 | KHEDER ALRAZAA |
| Issued | 9/12/2022 | APPLICANT |
| CofO in Progress | 12/29/2023 | MISAEL ESPARZA |
| CofO Issued | 2/29/2024 | RUBEN SALAS |
| Permit Finaled | 2/29/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2022 | CARLOS AGUILERA |
| Permit | Cleared | 2/24/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/28/2022 | CINDY JOSSELYN |
| Trees in Parkway | Cleared | 4/8/2022 | ADALBERTO VERA |
| Sewer availability | Cleared | 5/26/2022 | CARLOS AGUILERA |
| ZI | Cleared | 6/13/2022 | DANG NGUYEN |
| Low Impact Development | Cleared | 8/23/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/12/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/16/2022 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/21/2022 | Corrections Issued | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 9/26/2022 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/26/2022 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/28/2022 | Conditional Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/28/2022 | Off-Hour Fees Due | |
| Deputy Steel/Welding | 10/11/2022 | Conditional Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 10/20/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2022 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 10/20/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| MERV13>=Rough | 10/20/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 10/20/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 1/18/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 1/18/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/24/2023 | Approved | JACK KARGODORIAN |
| Deputy Wood Construction | 1/24/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 1/24/2023 | Approved | JACK KARGODORIAN |
| Green Building Rough | 1/24/2023 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 1/24/2023 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 1/24/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 1/30/2023 | Partial Approval | JACK KARGODORIAN |
| Insulation | 2/13/2023 | Approved | JACK KARGODORIAN |
| Shower Pan | 2/13/2023 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 2/21/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/28/2023 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Final | 9/1/2023 | Approved | JACK KARGODORIAN |
| HVAC-Final | 9/1/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 9/1/2023 | Approved | JACK KARGODORIAN |
| Final | 12/28/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Footing/Foundation/Slab | 12/28/2023 | Approved | MISAEL ESPARZA |
| Green Building Final | 12/28/2023 | Approved | MISAEL ESPARZA |
| MERV13>=Final | 12/28/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/28/2023 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 12/28/2023 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 12/28/2023 | Approved | MISAEL ESPARZA |