10010-10012 N MARKLEIN AVE 91345

Certificate Information: 10010-10012 N MARKLEIN AVE 91345

Application / Permit
21010-20000-06692
Plan Check / Job No.
B21VN17887
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan ADU addition. New A.D.U. (12' x 25') = 300 s.f. New Addition the mail house: - Add to (e) room 210 s.f. - Add new Dining room 290 s.f. New Storage 154 s.f. ATTACHED ADU PER ORDINANCE
Permit Issued
Issued on 1/3/2023
Issuing Office
Current Status
CofO Issued on 1/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2021 APPLICANT
Assigned to Plan Check Engineer 12/30/2021 VIVIAN LAO
Corrections Issued 12/31/2021 CARLOS MONTES
Applicant returned to address corrections 10/27/2022 VIVIAN LAO
Plan Check Approved 12/3/2022 DANIEL YIP
Issued 1/3/2023 APPLICANT
CofO in Progress 12/23/2024 JENNIFER RABUCHIN
Permit Finaled 1/2/2025 RUBEN SALAS
CofO Issued 1/2/2025 RUBEN SALAS
Permit Finaled 1/2/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/11/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 5/12/2022 ROMAN GUTIERREZ
Sewer availability Cleared 5/12/2022 ROMAN GUTIERREZ
Low Impact Development Cleared 11/28/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 12/1/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 12/1/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 12/1/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 12/1/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/20/2023 Corrections Issued JOHN COLEMAN
Pre-Inspection 1/21/2023 Off-Hour Fees Due
Footing/Foundation/Slab 7/28/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 1/12/2024 Approved JENNIFER RABUCHIN
Special/Order Compliance 1/12/2024 Corrections Issued JENNIFER RABUCHIN
Pre-Inspection 2/23/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 3/13/2024 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 3/13/2024 Corrections Issued JENNIFER RABUCHIN
Insulation 3/13/2024 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 3/13/2024 Partial Approval JENNIFER RABUCHIN
Insulation 3/18/2024 Approved JENNIFER RABUCHIN
Wood Frame 3/18/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 3/27/2024 Approved JOHN COLEMAN
Green Building Rough 3/27/2024 Approved JOHN COLEMAN
BUILDING-Rough-Frame 9/27/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/27/2024 Corrections Issued JENNIFER RABUCHIN
Final 9/27/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 9/27/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 9/27/2024 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 9/27/2024 Approved JENNIFER RABUCHIN
MERV13>=Rough 9/27/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/27/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/27/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 9/27/2024 Corrections Issued JENNIFER RABUCHIN
Deputy Wood Construction 10/4/2024 Conditional Approval ROBERT GOLD
ELECTRICAL-Final 10/31/2024 Approved JENNIFER RABUCHIN
Final 10/31/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/31/2024 Approved JENNIFER RABUCHIN
HVAC-Final 10/31/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/31/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/31/2024 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 10/31/2024 Approved JENNIFER RABUCHIN
Final 12/23/2024 OK to Issue CofO JENNIFER RABUCHIN