8220 N ENCINO AVE 91325
Certificate Information: 8220 N ENCINO AVE 91325
- Application / Permit
- 21010-20000-06670
- Plan Check / Job No.
- B21VN17852
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY DETACHED (32'-3"x21'-0"), 1196 SQFT ADU PER LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 8/23/2022
- Issuing Office
- Current Status
- CofO Issued on 1/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | PETER MOSESIAN |
| Corrections Issued | 2/4/2022 | PETER MOSESIAN |
| Quality Review Completed | 2/11/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 2/14/2022 | APPLICANT |
| Plan Check Approved | 6/29/2022 | PETER MOSESIAN |
| Issued | 8/23/2022 | APPLICANT |
| CofO in Progress | 1/3/2023 | RAUL OLAGI |
| CofO Issued | 1/14/2023 | MICHAEL SMITH |
| Permit Finaled | 1/14/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 3/10/2022 | LARRY REDDEN |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/31/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 4/24/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/26/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 6/13/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/31/2022 | Partial Approval | RAUL OLAGI |
| Sewer | 8/31/2022 | Approved | RAUL OLAGI |
| Special/Order Compliance | 8/31/2022 | Corrections Issued | RAUL OLAGI |
| Underground Mechanical | 8/31/2022 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 9/23/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2022 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/3/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 11/3/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 11/3/2022 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 11/3/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 11/7/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 11/7/2022 | Approved | RAUL OLAGI |
| Shower Pan | 11/7/2022 | Approved | RAUL OLAGI |
| Insulation | 11/9/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 11/14/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 12/5/2022 | Approved | RAUL OLAGI |
| Final | 12/5/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 12/5/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 12/5/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 12/5/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 12/5/2022 | Approved | RAUL OLAGI |
| Final | 12/27/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 12/27/2022 | Approved | RAUL OLAGI |
| Final | 1/3/2023 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 1/3/2023 | Approved | RAUL OLAGI |