5417 W LEXINGTON AVE 90029

Certificate Information: 5417 W LEXINGTON AVE 90029

Application / Permit
21010-20000-06618
Plan Check / Job No.
B21VN17766
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT ON TOP OF A NEW CARPORT AND ROOF DECK ( 42'-8"X29'-6") PER LAMC 12.22 A.33(c) and (d) FIRE SPRINKLER NFPA-13D
Permit Issued
Issued on 10/12/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2022 MOHAMMAD ESMAILI
Corrections Issued 1/23/2022 MOHAMMAD ESMAILI
Quality Review Completed 1/27/2022 OMID HEDAYAT
Building Plans Picked Up 1/28/2022 APPLICANT
Applicant returned to address corrections 3/7/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 3/10/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 3/16/2022 MOHAMMAD ESMAILI
Plan Check Approved 10/11/2022 MOHAMMAD ESMAILI
Issued 10/12/2022 APPLICANT
CofO in Progress 10/17/2024 CRAIG VAUGHAN
CofO Issued 11/14/2024 RUBEN SALAS
Permit Finaled 11/14/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/9/2022 STEVE MELGAR
"Q" conditions Cleared 2/10/2022 STEVEN WECHSLER
ZI Cleared 2/10/2022 STEVEN WECHSLER
ZI Cleared 2/10/2022 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 3/9/2022 STEVE MELGAR
Sewer availability Cleared 3/9/2022 STEVE MELGAR
ZI Cleared 3/17/2022 GRACIELA ACOSTA
Low Impact Development Cleared 7/11/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 9/29/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/26/2022 Corrections Issued JOAQUIN GREENOUGH
Pre-Inspection 10/27/2022 Approved JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 12/1/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 12/2/2022 Partial Approval JOAQUIN GREENOUGH
Deputy Steel/Welding 12/9/2022 Conditional Approval JOAQUIN GREENOUGH
Deputy Steel/Welding 12/13/2022 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 12/14/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 12/14/2022 Not Ready for Inspection JOAQUIN GREENOUGH
MERV13>=Rough 12/14/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Structural Steel Frame 12/14/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 12/14/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 12/17/2022 Partial Approval CARLOS MATAMOROS
Deputy Steel/Welding 12/22/2022 Conditional Approval JOAQUIN GREENOUGH
Deputy Steel/Welding 12/30/2022 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 1/19/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 1/23/2023 Approved BRIAN SULLIVAN
Piling/Pier/Caisson 1/23/2023 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Partial Approval JOAQUIN GREENOUGH
Deputy Wood Construction 2/13/2023 Conditional Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 2/14/2023 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 2/14/2023 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 2/14/2023 Not Ready for Inspection RAUL BARAJAS
MERV13>=Rough 2/14/2023 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 2/14/2023 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 3/3/2023 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 3/3/2023 Off-Hour Fees Due
ELECTRICAL-Rough 3/14/2023 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Rough 3/14/2023 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 3/14/2023 Corrections Issued ALIZAH MAYAGOITIA
Insulation 3/16/2023 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 3/21/2023 Approved JOAQUIN GREENOUGH
HVAC-Rough 3/21/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 3/21/2023 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 3/22/2023 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 3/22/2023 Approved JOAQUIN GREENOUGH
MERV13>=Rough 3/22/2023 Approved JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 3/22/2023 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 4/3/2023 Approved JOAQUIN GREENOUGH
Insulation 4/10/2023 Approved RAUL BARAJAS
Drywall Nailing 4/14/2023 Approved RAUL BARAJAS
Interior/Exterior Lathing 4/14/2023 Approved RAUL BARAJAS
Interior/Exterior Lathing 4/19/2023 Approved JOAQUIN GREENOUGH
Gas Test 8/4/2023 Approved JOAQUIN GREENOUGH
Service/Power Release 8/4/2023 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Final 8/14/2023 Approved JOAQUIN GREENOUGH
HVAC-Final 8/14/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Final 8/14/2023 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 8/15/2023 Approved JOAQUIN GREENOUGH
Underground Mechanical 8/15/2023 Partial Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 8/17/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 8/17/2023 Approved JOAQUIN GREENOUGH
Underground Mechanical 8/17/2023 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Not Ready STUART CHAPMAN
ELECTRICAL-Final 9/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Final 9/12/2023 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 9/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Final 9/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
MERV13>=Final 9/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Final 9/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 9/12/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Service/Power Release 9/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 9/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Structural Steel Frame 9/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Final 10/26/2023 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Final 10/26/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Final 10/26/2023 Approved JOAQUIN GREENOUGH
Final 4/17/2024 Corrections Issued ROY SPAULDING
Green Building Final 4/17/2024 Approved ROY SPAULDING
MERV13>=Final 4/17/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 4/17/2024 SGSOV Approved ROY SPAULDING
Service/Power Release 4/17/2024 Not Ready for Inspection ROY SPAULDING
Smoke Detectors 4/17/2024 Approved ROY SPAULDING
Structural Steel Frame 4/17/2024 Approved ROY SPAULDING
Service/Power Release 10/8/2024 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 10/16/2024 Approved CRAIG VAUGHAN
Final 10/16/2024 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 10/16/2024 Approved CRAIG VAUGHAN
PLUMBING-Final 10/16/2024 Approved CRAIG VAUGHAN
Service/Power Release 10/16/2024 Approved CRAIG VAUGHAN