5417 W LEXINGTON AVE 90029
Certificate Information: 5417 W LEXINGTON AVE 90029
- Application / Permit
- 21010-20000-06618
- Plan Check / Job No.
- B21VN17766
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT ON TOP OF A NEW CARPORT AND ROOF DECK ( 42'-8"X29'-6") PER LAMC 12.22 A.33(c) and (d) FIRE SPRINKLER NFPA-13D
- Permit Issued
- Issued on 10/12/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 1/23/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 1/27/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 1/28/2022 | APPLICANT |
| Applicant returned to address corrections | 3/7/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 3/10/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 3/16/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 10/11/2022 | MOHAMMAD ESMAILI |
| Issued | 10/12/2022 | APPLICANT |
| CofO in Progress | 10/17/2024 | CRAIG VAUGHAN |
| CofO Issued | 11/14/2024 | RUBEN SALAS |
| Permit Finaled | 11/14/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/9/2022 | STEVE MELGAR |
| "Q" conditions | Cleared | 2/10/2022 | STEVEN WECHSLER |
| ZI | Cleared | 2/10/2022 | STEVEN WECHSLER |
| ZI | Cleared | 2/10/2022 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 3/9/2022 | STEVE MELGAR |
| ZI | Cleared | 3/17/2022 | GRACIELA ACOSTA |
| Low Impact Development | Cleared | 7/11/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 9/29/2022 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/26/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Pre-Inspection | 10/27/2022 | Approved | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/1/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 12/2/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Deputy Steel/Welding | 12/9/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Steel/Welding | 12/13/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 12/14/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 12/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| MERV13>=Rough | 12/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Structural Steel Frame | 12/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 12/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 12/17/2022 | Partial Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 12/22/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Steel/Welding | 12/30/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 1/19/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 1/23/2023 | Approved | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 1/23/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 2/13/2023 | Conditional Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 2/14/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 2/14/2023 | Not Ready for Inspection | RAUL BARAJAS |
| MERV13>=Rough | 2/14/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 2/14/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2023 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2023 | Off-Hour Fees Due | |
| ELECTRICAL-Rough | 3/14/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Rough | 3/14/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/14/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Insulation | 3/16/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 3/21/2023 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 3/21/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/21/2023 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/22/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 3/22/2023 | Approved | JOAQUIN GREENOUGH |
| MERV13>=Rough | 3/22/2023 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 3/22/2023 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/3/2023 | Approved | JOAQUIN GREENOUGH |
| Insulation | 4/10/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 4/14/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 4/14/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 4/19/2023 | Approved | JOAQUIN GREENOUGH |
| Gas Test | 8/4/2023 | Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 8/4/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 8/14/2023 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 8/14/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 8/14/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/15/2023 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 8/15/2023 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/17/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/17/2023 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 8/17/2023 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 9/1/2023 | SGSOV Not Ready | STUART CHAPMAN |
| ELECTRICAL-Final | 9/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 9/12/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 9/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Final | 9/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| MERV13>=Final | 9/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 9/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 9/12/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 9/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 9/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Structural Steel Frame | 9/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 10/26/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Final | 10/26/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 10/26/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 4/17/2024 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 4/17/2024 | Approved | ROY SPAULDING |
| MERV13>=Final | 4/17/2024 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 4/17/2024 | SGSOV Approved | ROY SPAULDING |
| Service/Power Release | 4/17/2024 | Not Ready for Inspection | ROY SPAULDING |
| Smoke Detectors | 4/17/2024 | Approved | ROY SPAULDING |
| Structural Steel Frame | 4/17/2024 | Approved | ROY SPAULDING |
| Service/Power Release | 10/8/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 10/16/2024 | Approved | CRAIG VAUGHAN |
| Final | 10/16/2024 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 10/16/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 10/16/2024 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 10/16/2024 | Approved | CRAIG VAUGHAN |