7931 N RIVERTON AVE 91352

Certificate Information: 7931 N RIVERTON AVE 91352

Application / Permit
21010-20000-06602
Plan Check / Job No.
B21VN17739
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan NEW 2-STORY DETACHED ACCESSORY DWELLING UNIT WITH ATTACHED COVERED PATIO AT REAR OF LOT
Permit Issued
Issued on 9/7/2022
Issuing Office
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2021 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 PRANITA SHAH
Corrections Issued 1/27/2022 PRANITA SHAH
Quality Review Completed 2/3/2022 MICHAEL PEREZ
Applicant returned to address corrections 5/5/2022 PRANITA SHAH
Applicant returned to address corrections 8/5/2022 PRANITA SHAH
Plan Check Approved 8/8/2022 PRANITA SHAH
Issued 9/7/2022 APPLICANT
CofO in Progress 10/9/2024 MATTHEW NELSON
Permit Finaled 10/25/2024 DANIEL ORRANTE
CofO Issued 10/25/2024 DANIEL ORRANTE
Permit Finaled 10/25/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/4/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/18/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/18/2022 DAGOVERTO GUERRERO
Disturb/Remove Protected Trees Cleared 7/22/2022 ADALBERTO VERA
Low Impact Development Cleared 7/22/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 7/28/2022 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/14/2022 Partial Approval CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 11/23/2022 Approved MATTHEW NELSON
Footing/Foundation/Slab 12/13/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/17/2023 Partial Approval MATTHEW NELSON
Green Building Rough 4/17/2023 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 4/17/2023 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 9/8/2023 Corrections Issued KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 9/8/2023 Not Ready for Inspection KEVIN BERBERYAN
Green Building Rough 9/8/2023 Approved KEVIN BERBERYAN
Verify Sprinkler Sign Off 9/8/2023 Not Ready for Inspection KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Corrections Issued DAVID MATSON
Pre-Inspection 9/12/2023 Not Ready for Inspection DAVID MATSON
BUILDING-Rough-Frame 9/21/2023 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Partial Approval DAVID ANDERSON
Special/Order Compliance 9/21/2023 Corrections Issued DAVID ANDERSON
Insulation 10/5/2023 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 10/5/2023 Partial Approval CHRISTOPHER ROJAS
Drywall Nailing 10/16/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 11/15/2023 Approved CHRISTOPHER ROJAS
Gas Test 7/2/2024 Not Ready for Inspection MATTHEW NELSON
Service/Power Release 7/2/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/7/2024 Approved MATTHEW NELSON
Final 10/7/2024 OK to Issue CofO MATTHEW NELSON
Green Building Final 10/7/2024 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/7/2024 SGSOV Approved MATTHEW NELSON
Smoke Detectors 10/7/2024 Approved MATTHEW NELSON
Service/Power Release 10/21/2024 Approved MATTHEW NELSON