5323 E TEMPLETON ST 90032
Certificate Information: 5323 E TEMPLETON ST 90032
- Application / Permit
- 21010-20000-06549
- Plan Check / Job No.
- B21VN17628
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 26'-6" X 53'-0" IRREG SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 7/6/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2021 | ARTIN ZARUKIAN |
| Corrections Issued | 12/29/2021 | ARTIN ZARUKIAN |
| Plan Check Approved | 4/11/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/12/2022 | APPLICANT |
| Issued | 7/6/2022 | APPLICANT |
| CofO in Progress | 2/22/2024 | LILIANA PORTILLO |
| Permit Finaled | 3/1/2024 | DEROLD HAUFF |
| CofO Issued | 3/1/2024 | DEROLD HAUFF |
| Permit Finaled | 3/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/19/2022 | KHOUNG LE |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | KHOUNG LE |
| Sewer availability | Cleared | 1/26/2022 | KHOUNG LE |
| Low Impact Development | Cleared | 3/17/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 3/22/2022 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 3/23/2022 | CINDY JOSSELYN |
| GPI Written Notices | Cleared | 4/11/2022 | JEROME MAGAT PALMA |
| Grading Pre-Inspection | Cleared | 4/11/2022 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/24/2022 | Conditional Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2022 | Not Ready for Inspection | AMY COLIN |
| Underground Mechanical | 9/1/2022 | Not Ready for Inspection | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Partial Approval | AMY COLIN |
| Underground Mechanical | 10/5/2022 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2022 | Partial Approval | AMY COLIN |
| Insulation | 10/7/2022 | Partial Approval | AMY COLIN |
| Wood Frame | 10/7/2022 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2022 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2022 | Corrections Issued | AMY COLIN |
| BUILDING-Rough-Frame | 11/21/2022 | Not Ready for Inspection | AMY COLIN |
| ELECTRICAL-Rough | 11/21/2022 | Not Ready for Inspection | AMY COLIN |
| Green Building Rough | 11/21/2022 | Not Ready for Inspection | AMY COLIN |
| HVAC-Rough | 11/21/2022 | Not Ready for Inspection | AMY COLIN |
| PLUMBING-Rough | 11/21/2022 | Not Ready for Inspection | AMY COLIN |
| Verify Sprinkler Sign Off | 11/21/2022 | Not Ready for Inspection | AMY COLIN |
| Rough-Elec/Plmb/HVAC | 11/23/2022 | Corrections Issued | RUBEN SALAS |
| BUILDING-Rough-Frame | 11/28/2022 | Approved | AMY COLIN |
| Green Building Rough | 11/28/2022 | Not Ready for Inspection | AMY COLIN |
| Rough-Elec/Plmb/HVAC | 11/28/2022 | Approved | AMY COLIN |
| Verify Sprinkler Sign Off | 11/28/2022 | Approved | AMY COLIN |
| Insulation | 11/30/2022 | Not Ready for Inspection | AMY COLIN |
| Interior/Exterior Lathing | 11/30/2022 | Approved | AMY COLIN |
| Drywall Nailing | 12/2/2022 | Not Ready for Inspection | AMY COLIN |
| Green Building Rough | 12/2/2022 | Not Ready for Inspection | AMY COLIN |
| Shower Pan | 12/2/2022 | Not Ready for Inspection | AMY COLIN |
| Insulation | 12/16/2022 | Conditional Approval | AMY COLIN |
| Drywall Nailing | 12/20/2022 | Not Ready for Inspection | AMY COLIN |
| Green Building Rough | 12/20/2022 | Not Ready for Inspection | AMY COLIN |
| BUILDING-Rough-Frame | 12/22/2022 | Approved | AMY COLIN |
| Drywall Nailing | 12/22/2022 | Partial Approval | AMY COLIN |
| Green Building Rough | 12/22/2022 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 1/26/2023 | Not Ready for Inspection | AMY COLIN |
| Shower Pan | 1/26/2023 | Not Ready for Inspection | AMY COLIN |
| Interior/Exterior Lathing | 2/8/2023 | Approved | RUBEN SALAS |
| Shower Pan | 2/8/2023 | Approved | RUBEN SALAS |
| Drywall Nailing | 12/7/2023 | Approved | AMY COLIN |
| Final | 12/7/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 12/7/2023 | Approved | AMY COLIN |
| Green Building Final | 12/7/2023 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 12/7/2023 | SGSOV Not Ready | AMY COLIN |
| Service/Power Release | 12/7/2023 | Corrections Issued | AMY COLIN |
| Smoke Detectors | 12/7/2023 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 12/28/2023 | SGSOV Not Ready | AMY COLIN |
| Final | 1/17/2024 | Not Ready for Inspection | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 1/17/2024 | SGSOV Not Ready | AMY COLIN |
| Service/Power Release | 1/17/2024 | Not Ready for Inspection | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 2/1/2024 | SGSOV Not Ready | JOSH MEISTER |
| Final | 2/6/2024 | Corrections Issued | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 2/6/2024 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 2/6/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 2/21/2024 | Approved | LILIANA PORTILLO |
| Final | 2/21/2024 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 2/21/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 2/21/2024 | Approved | LILIANA PORTILLO |