16304 W CHATSWORTH ST 91344

Certificate Information: 16304 W CHATSWORTH ST 91344

Application / Permit
21010-20000-06539
Plan Check / Job No.
B21VN17601
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 2-STORY ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 4/15/2022
Issuing Office
Current Status
CofO Issued on 6/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 FARSHAD ALIMOHAMADI
Corrections Issued 1/27/2022 FARSHAD ALIMOHAMADI
Quality Review Completed 1/28/2022 SAI KHUM
Applicant returned to address corrections 3/4/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 3/29/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 3/30/2022 FARSHAD ALIMOHAMADI
Issued 4/15/2022 APPLICANT
CofO in Progress 5/13/2024 JAVIER RAMOS JR
Permit Finaled 6/29/2024 RUBEN SALAS
CofO Issued 6/29/2024 RUBEN SALAS
Permit Finaled 6/29/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/1/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/2/2022 CARLOS AGUILERA
Sewer availability Cleared 2/2/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 3/11/2022 CINDY JOSSELYN
Low Impact Development Cleared 3/11/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 3/14/2022 CARLOS AGUILERA

Contact Information

Contractor Jrl Construction; Lic. No.: 1079051-B       ,
Engineer Crook,, Barrett Cameron; Lic. No.: NA57196       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/23/2022 Conditional Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/6/2022 Corrections Issued JAVIER RAMOS JR
Deputy Wood Construction 7/18/2022 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 7/26/2022 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/26/2022 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 7/26/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 7/26/2022 Corrections Issued JAVIER RAMOS JR
Verify Sprinkler Sign Off 7/26/2022 Approved JAVIER RAMOS JR
Wood Frame 7/26/2022 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 9/2/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 9/2/2022 Corrections Issued JAVIER RAMOS JR
Gas Test 9/2/2022 Partial Approval JAVIER RAMOS JR
HVAC-Rough 9/2/2022 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 9/2/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 9/21/2022 Approved JAVIER RAMOS JR
HVAC-Rough 9/21/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 11/4/2022 Approved JAVIER RAMOS JR
Green Building Rough 11/4/2022 Approved JAVIER RAMOS JR
Insulation 11/4/2022 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 11/4/2022 Partial Approval JAVIER RAMOS JR
Drywall Nailing 1/4/2023 Partial Inspection JAVIER RAMOS JR
Shower Pan 3/14/2023 Not Ready for Inspection DAVID ANDERSON
Gas Test 5/11/2023 Not Ready for Inspection JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 5/11/2023 Not Ready for Inspection JAVIER RAMOS JR
Sewer 5/11/2023 Approved JAVIER RAMOS JR
Shower Pan 5/11/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/6/2023 Approved JAVIER RAMOS JR
Gas Test 11/17/2023 Partial Approval JAVIER RAMOS JR
Underground Mechanical 11/17/2023 Approved JAVIER RAMOS JR
Pre-Inspection 1/24/2024 Approved JAVIER RAMOS JR
Final 4/12/2024 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/12/2024 SGSOV Not Ready JAVIER RAMOS JR
Service/Power Release 4/12/2024 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 4/12/2024 Not Ready for Inspection JAVIER RAMOS JR
Final 4/26/2024 Not Ready for Inspection JAVIER RAMOS JR
Gas Test 4/26/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/26/2024 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 4/26/2024 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 4/26/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/10/2024 Approved JAVIER RAMOS JR
Final 5/10/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 5/10/2024 Approved JAVIER RAMOS JR
HVAC-Final 5/10/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 5/10/2024 Approved JAVIER RAMOS JR
Service/Power Release 5/10/2024 Approved JAVIER RAMOS JR