19429 W ARCHWOOD ST 91335
Certificate Information: 19429 W ARCHWOOD ST 91335
- Application / Permit
- 21010-20000-06533
- Plan Check / Job No.
- B21VN17589
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ECPC: PROPOSED 21' X 25' ACCESSORY DWELLING UNIT, PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c) AND (g). ALL WORK PER WFPP.
- Permit Issued
- Issued on 6/10/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2021 | LUISANGEL VALENZUELA |
| Corrections Issued | 12/30/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 5/29/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 6/10/2022 | LUISANGEL VALENZUELA |
| Issued | 6/10/2022 | APPLICANT |
| Building Plans Picked Up | 6/13/2022 | APPLICANT |
| CofO in Progress | 1/27/2023 | JEFFREY BULL |
| Permit Finaled | 2/3/2023 | JOHN JANSON |
| CofO Issued | 2/3/2023 | JOHN JANSON |
| Permit Finaled | 2/3/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/1/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 4/5/2022 | SARAH YOUSSEF |
| Construction near power lines | Cleared | 4/23/2022 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 5/24/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/14/2022 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 10/19/2022 | Partial Approval | JEFFREY BULL |
| Green Building Rough | 10/19/2022 | Approved | JEFFREY BULL |
| Verify Sprinkler Sign Off | 10/19/2022 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 11/7/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 11/7/2022 | Approved | JEFFREY BULL |
| HVAC-Rough | 11/7/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 11/7/2022 | Approved | JEFFREY BULL |
| Insulation | 11/15/2022 | Approved | JEFFREY BULL |
| Drywall Nailing | 11/30/2022 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 12/23/2022 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Final | 1/12/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/12/2023 | Approved | VINCENT HANLEY |
| Final | 1/24/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 1/24/2023 | Not Ready for Inspection | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 1/24/2023 | SGSOV Not Ready | JEFFREY BULL |
| Service/Power Release | 1/24/2023 | Not Ready for Inspection | JEFFREY BULL |
| Smoke Detectors | 1/24/2023 | Approved | JEFFREY BULL |
| Final | 1/26/2023 | Not Ready for Inspection | JEFFREY BULL |
| Pre-Inspection | 1/26/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Approved | JEFFREY BULL |
| Final | 1/27/2023 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 1/27/2023 | Approved | JEFFREY BULL |