612 1/2 E 118TH ST 90059

Certificate Information: 612 1/2 E 118TH ST 90059

Application / Permit
21010-20000-06532
Plan Check / Job No.
B21VN17585
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 28'-0" x 32'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING. The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 6/7/2023
Issuing Office
Current Status
CofO Issued on 10/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 RAPHAEL ROSAS
Corrections Issued 12/31/2021 RAPHAEL ROSAS
Building Plans Picked Up 1/3/2022 APPLICANT
Applicant returned to address corrections 2/17/2023 SARKIS HARABEDIAN
Plan Check Approved 2/22/2023 LUISANGEL VALENZUELA
Issued 6/7/2023 APPLICANT
CofO in Progress 10/8/2025 ANTHONY EGSON
Permit Finaled 10/14/2025 ANSON MAGLASANG
CofO Issued 10/14/2025 ANSON MAGLASANG
Permit Finaled 10/14/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 1/11/2022 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 1/11/2022 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 1/14/2022 MARKOS PEREZ-BRAN
Sewer availability Cleared 1/14/2022 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/21/2023 Corrections Issued JOHN KLARIN
Pre-Inspection 7/19/2023 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 10/10/2023 Approved JOHN KLARIN
Footing/Foundation/Slab 10/10/2023 Approved JOHN KLARIN
Sewer 10/25/2023 Approved JAMES CHAVEZ
Underground Mechanical 10/25/2023 Approved JAMES CHAVEZ
Deputy Steel/Welding 11/14/2023 Approved JOHN KLARIN
Wood Frame 11/22/2023 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 3/27/2024 Corrections Issued BEN MOLSTAD
Light Gage Steel Frame 3/27/2024 Approved BEN MOLSTAD
PLUMBING-Rough 3/27/2024 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 4/1/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 4/1/2024 Corrections Issued BEN MOLSTAD
Wood Frame 4/1/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 6/4/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 6/4/2024 Corrections Issued BEN MOLSTAD
Rough-Elec/Plmb/HVAC 7/10/2024 Corrections Issued BEN MOLSTAD
Special/Order Compliance 7/10/2024 Partial Inspection ANSON MAGLASANG
BUILDING-Rough-Frame 12/13/2024 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 12/13/2024 Partial Inspection JOSEPH MCGARRY
HVAC-Rough 12/13/2024 Approved JOSEPH MCGARRY
Insulation 12/13/2024 Conditional Approval JOSEPH MCGARRY
Interior/Exterior Lathing 12/13/2024 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 12/13/2024 Approved JOSEPH MCGARRY
Drywall Nailing 1/16/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 1/16/2025 Approved ANTHONY EGSON
Green Building Rough 1/16/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 5/16/2025 Partial Approval ANTHONY EGSON
ELECTRICAL-Final 5/16/2025 Corrections Issued ANTHONY EGSON
Final 5/16/2025 Corrections Issued ANTHONY EGSON
Green Building Final 5/16/2025 Corrections Issued ANTHONY EGSON
HVAC-Final 5/16/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Final 5/16/2025 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 5/16/2025 SGSOV Approved ANTHONY EGSON
Service/Power Release 5/16/2025 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 5/16/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 10/1/2025 Approved ANTHONY EGSON
Final 10/1/2025 Corrections Issued ANTHONY EGSON
Green Building Final 10/1/2025 Approved ANTHONY EGSON
Service/Power Release 10/1/2025 Approved ANTHONY EGSON
Drywall Nailing 10/6/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 10/6/2025 Approved ANTHONY EGSON
Final 10/6/2025 OK to Issue CofO ANTHONY EGSON
HVAC-Final 10/6/2025 Approved ANTHONY EGSON