13167 W GARBER ST 91331
Certificate Information: 13167 W GARBER ST 91331
- Application / Permit
- 21010-20000-06531
- Plan Check / Job No.
- B21VN17584
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY (40'-0"x24'-0"), 846 SQ. FT. ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 5/6/2022
- Issuing Office
- Current Status
- Issued on 5/6/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2021 | PETER MOSESIAN |
| Corrections Issued | 1/10/2022 | PETER MOSESIAN |
| Building Plans Picked Up | 1/14/2022 | APPLICANT |
| Issued | 5/6/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/19/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 1/20/2022 | JOSE DUARTE-DIAZ |
| Clean Up Green Up | Cleared | 1/25/2022 | DANG NGUYEN |
| ZI | Cleared | 1/25/2022 | DANG NGUYEN |
| Hydrant and Access approval | Cleared | 3/11/2022 | LARRY REDDEN |
| Low Impact Development | Cleared | 4/25/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 4/29/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 14545 VICTORY BLVD 405 VAN NUYS, CA 91411 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/10/2022 | Partial Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 6/29/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Sewer | 6/29/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 6/29/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 6/30/2022 | No Access for Inspection | MATT KELLERMAN |
| METHANE-Subgrade | 6/30/2022 | No Access for Inspection | MATT KELLERMAN |
| Underground Mechanical | 6/30/2022 | No Access for Inspection | MATT KELLERMAN |
| Deputy Methane Barrier | 7/13/2022 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 7/15/2022 | Corrections Issued | MICHEL ABAJAN |
| METHANE-Barrier | 7/15/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Subgrade | 7/15/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 8/9/2022 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 8/9/2022 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 8/9/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/7/2022 | Partial Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 9/7/2022 | Partial Inspection | MICHEL ABAJAN |
| METHANE-Rough | 9/7/2022 | Partial Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 9/7/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/30/2022 | No Access for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/30/2022 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Rough | 9/30/2022 | No Access for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 9/30/2022 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 9/30/2022 | No Access for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 10/4/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 10/4/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/4/2022 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 10/4/2022 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/7/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/7/2022 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 11/7/2022 | Approved | MICHEL ABAJAN |
| Insulation | 1/30/2023 | Corrections Issued | WILLIAM WREN |
| Insulation | 2/2/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/10/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 12/13/2023 | Approved | MICHEL ABAJAN |
| Final | 12/13/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 12/13/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 12/13/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 12/13/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 12/13/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 12/13/2023 | Approved | MICHEL ABAJAN |
| Final | 2/15/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Service/Power Release | 2/15/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/3/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Grounding or Bonding | 4/3/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 6/2/2026 | Corrections Issued | MICHEL ABAJAN |
| Service/Power Release | 6/2/2026 | Corrections Issued | MICHEL ABAJAN |