6942 N AURA AVE 91335
Certificate Information: 6942 N AURA AVE 91335
- Application / Permit
- 21010-20000-06527
- Plan Check / Job No.
- B21VN17575
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EXISTING DETACHED GARAGE CONVERTED TO DETACHED A.D.U. PER ORDINANCE
- Permit Issued
- Issued on 1/11/2022
- Issuing Office
- Current Status
- CofO Issued on 12/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2021 | APPLICANT |
| Corrections Issued | 12/18/2021 | CARLOS MONTES |
| Assigned to Plan Check Engineer | 12/20/2021 | CARLOS MONTES |
| Corrections Issued | 12/20/2021 | JOE VO |
| Plan Check Approved | 1/4/2022 | CARLOS MONTES |
| Issued | 1/11/2022 | APPLICANT |
| CofO in Progress | 8/17/2022 | JEFFREY BULL |
| Permit Finaled | 12/9/2022 | MICHAEL SMITH |
| CofO Issued | 12/9/2022 | MICHAEL SMITH |
| Permit Finaled | 12/9/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/23/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/23/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/10/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/11/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/4/2022 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 4/4/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Wood Frame | 4/4/2022 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/7/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/7/2022 | Approved | VINCENT HANLEY |
| Wood Frame | 4/7/2022 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/21/2022 | Partial Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/21/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/21/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 4/21/2022 | Approved | VINCENT HANLEY |
| Insulation | 4/21/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 4/28/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 5/3/2022 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 5/3/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/10/2022 | Approved | VINCENT HANLEY |
| Gas Test | 6/13/2022 | Corrections Issued | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 6/13/2022 | SGSOV Not Ready | MORRIS JACKSON |
| Sewer | 6/13/2022 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 7/26/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 7/26/2022 | Approved | JEFFREY BULL |
| Final | 7/26/2022 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Final | 7/26/2022 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Final | 7/26/2022 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Final | 7/26/2022 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 7/26/2022 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 7/26/2022 | Approved | JEFFREY BULL |
| Final | 8/16/2022 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 8/16/2022 | Approved | JEFFREY BULL |
| HVAC-Final | 8/16/2022 | Approved | JEFFREY BULL |
| Service/Power Release | 8/29/2022 | Not Ready for Inspection | JEFFREY BULL |
| Service/Power Release | 9/6/2022 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Final | 9/9/2022 | Approved | JEFFREY BULL |
| Service/Power Release | 9/9/2022 | Approved | JEFFREY BULL |