16653 W MORRISON ST 91436
Certificate Information: 16653 W MORRISON ST 91436
- Application / Permit
- 21010-20000-06463
- Plan Check / Job No.
- B21VN17348
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 69'-8" X 47'-7" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/26/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2021 | SELLA BENYAMIN |
| Corrections Issued | 12/28/2021 | SELLA BENYAMIN |
| Quality Review Completed | 12/30/2021 | STEVEN KIM |
| Building Plans Picked Up | 1/5/2022 | APPLICANT |
| Plan Check Approved | 8/18/2022 | SELLA BENYAMIN |
| Issued | 8/26/2022 | APPLICANT |
| CofO in Progress | 8/10/2023 | VINCENT HANLEY |
| CofO Issued | 9/5/2023 | JOHN JANSON |
| Permit Finaled | 9/5/2023 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 4/21/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 5/10/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/13/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 5/21/2022 | LARRY REDDEN |
| Low Impact Development | Cleared | 8/2/2022 | MARCO SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Ricardo Ray; Lic. No.: C66957 | 27702 QUINCY ST CASTAIC, CA 91384 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/23/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Pre-Inspection | 9/23/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 10/3/2022 | Partial Approval | VINCENT HANLEY |
| Sewer | 10/5/2022 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 10/6/2022 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 10/6/2022 | Partial Approval | VINCENT HANLEY |
| Deputy Reinf. Concrete | 10/13/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 10/13/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Partial Approval | VINCENT HANLEY |
| Pre-Inspection | 11/23/2022 | Corrections Issued | VINCENT HANLEY |
| Pre-Inspection | 11/23/2022 | Partial Inspection | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2022 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 1/17/2023 | Approved | VINCENT HANLEY |
| HVAC-Rough | 1/20/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 1/20/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/10/2023 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/14/2023 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 2/14/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/14/2023 | Approved | VINCENT HANLEY |
| Wood Frame | 2/14/2023 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/24/2023 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 2/24/2023 | Approved | JESUS PINEDA |
| Insulation | 2/27/2023 | Approved | VINCENT HANLEY |
| Drywall Nailing | 3/6/2023 | Approved | VINCENT HANLEY |
| Special/Order Compliance | 3/6/2023 | Partial Inspection | JUSTIN HAWLEY |
| HVAC-Final | 6/14/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 6/14/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 6/16/2023 | Approved | VINCENT HANLEY |
| Service/Power Release | 6/16/2023 | Approved | VINCENT HANLEY |
| Final | 7/14/2023 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 7/14/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/14/2023 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 7/14/2023 | Approved | VINCENT HANLEY |
| Smoke Detectors | 7/14/2023 | Approved | VINCENT HANLEY |
| Final | 8/10/2023 | OK to Issue CofO | VINCENT HANLEY |