16735 W TULSA ST 91344

Certificate Information: 16735 W TULSA ST 91344

Application / Permit
21010-20000-06460
Plan Check / Job No.
B21VN17316
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN Detached 1200 SF ADU PER ORDIANCE AND LAMC 12.22 A33(c)&(d). “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.”
Permit Issued
Issued on 9/23/2022
Issuing Office
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 ZAW HAN
Corrections Issued 1/20/2022 ZAW HAN
Quality Review Completed 1/26/2022 SAI KHUM
Applicant returned to address corrections 6/28/2022 ZAW HAN
Plan Check Approved 7/28/2022 ZAW HAN
Issued 9/23/2022 APPLICANT
CofO in Progress 3/9/2026 CHRISTOPHER ROJAS
CofO Issued 4/2/2026 RUBEN SALAS
Permit Finaled 4/2/2026 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/8/2022 CINDY JOSSELYN
Address approval Cleared 6/24/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 6/24/2022 JOSE DUARTE-DIAZ
Permit Cleared 6/24/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 6/24/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 6/24/2022 JOSE DUARTE-DIAZ
Green Code Cleared 7/28/2022 ZAW HAN

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040
Engineer Roberts,, Jeffrey Allan; Lic. No.: NA56881       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/4/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 10/4/2022 Partial Approval JAVIER RAMOS JR
Pre-Inspection 10/4/2022 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 10/13/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Partial Approval JORDAN KUTZLY
PLUMBING-Rough 11/21/2022 Not Ready for Inspection JORDAN KUTZLY
Deputy Wood Construction 12/1/2022 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 12/13/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 Partial Approval JAVIER RAMOS JR
HVAC-Rough 12/13/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 12/13/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/20/2022 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Approved JAVIER RAMOS JR
Green Building Rough 12/20/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 12/20/2022 Approved JAVIER RAMOS JR
Shower Pan 12/20/2022 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 12/20/2022 Approved JAVIER RAMOS JR
Insulation 12/28/2022 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 1/4/2023 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 1/4/2023 Approved CHRISTOPHER DELLEFIELD
Insulation 1/4/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 1/13/2023 Not Ready for Inspection JAVIER RAMOS JR
Drywall Nailing 1/13/2023 Corrections Issued JAVIER RAMOS JR
Drywall Nailing 1/19/2023 Not Ready for Inspection JAVIER RAMOS JR
Drywall Nailing 2/16/2023 Approved JAVIER RAMOS JR
Gas Test 2/16/2023 Approved JAVIER RAMOS JR
Pre-Inspection 2/16/2023 Approved JAVIER RAMOS JR
HVAC-Final 2/22/2023 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Final 2/22/2023 Not Ready for Inspection JAVIER RAMOS JR
Pre-Inspection 2/22/2023 Approved JAVIER RAMOS JR
Special/Order Compliance 2/22/2023 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/10/2023 SGSOV Not Ready JAVIER RAMOS JR
BUILDING-Rough-Frame 7/6/2023 Approved JAVIER RAMOS JR
Final 7/6/2023 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 7/6/2023 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 7/6/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 7/6/2023 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 7/6/2023 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 7/6/2023 Not Ready for Inspection JAVIER RAMOS JR
Final 7/13/2023 Partial Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 7/13/2023 Not Ready for Inspection JAVIER RAMOS JR
Service/Power Release 7/13/2023 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 7/13/2023 Approved JAVIER RAMOS JR
Final 9/14/2023 No Access for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 9/14/2023 No Access for Inspection MISAEL ESPARZA
Service/Power Release 9/14/2023 No Access for Inspection MISAEL ESPARZA
Final 10/7/2025 No Access for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 10/7/2025 No Access for Inspection CHRISTOPHER ROJAS
Service/Power Release 10/7/2025 No Access for Inspection CHRISTOPHER ROJAS
Final 11/17/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 11/17/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Service/Power Release 11/17/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 2/17/2026 Partial Inspection MISAEL ESPARZA
Footing/Foundation/Slab 2/17/2026 Partial Inspection MISAEL ESPARZA
Service/Power Release 2/17/2026 Partial Inspection MISAEL ESPARZA
Final 2/20/2026 OK to Issue CofO CHRISTOPHER ROJAS
Footing/Foundation/Slab 2/20/2026 Approved CHRISTOPHER ROJAS
Service/Power Release 2/20/2026 Approved CHRISTOPHER ROJAS
Final 2/26/2026 Corrections Issued CHRISTOPHER ROJAS
Final 3/5/2026 Partial Approval CHRISTOPHER ROJAS