9118 N ENCINO AVE 91325
Certificate Information: 9118 N ENCINO AVE 91325
- Application / Permit
- 21010-20000-06456
- Plan Check / Job No.
- B21VN17305
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW ACCESSORY DWELLING UNIT ADDITION TO (E) DETACHED GARAGE PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 11/15/2022
- Issuing Office
- Current Status
- CofO Issued on 9/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2022 | KEVIN MORALES |
| Corrections Issued | 1/3/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 5/18/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 5/23/2022 | KEVIN MORALES |
| Plan Check Approved | 10/7/2022 | KEVIN MORALES |
| Issued | 11/15/2022 | APPLICANT |
| CofO in Progress | 8/22/2023 | JAVIER RAMOS JR |
| Permit Finaled | 9/29/2023 | RUBEN SALAS |
| CofO Issued | 9/29/2023 | RUBEN SALAS |
| Permit Finaled | 9/29/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 1/7/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 5/18/2022 | KURT CORRAL |
| Private sewage disp. approval | Cleared | 9/29/2022 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mixter,, Thomas J; Lic. No.: C51041 | 2345 COUNTY RD 630 DEL RIO, TX 78840 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/23/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 3/7/2023 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 3/7/2023 | Approved | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 3/8/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/9/2023 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/18/2023 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2023 | Partial Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/18/2023 | Approved | JAVIER RAMOS JR |
| Sewer | 4/18/2023 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/10/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/10/2023 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/10/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/10/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/10/2023 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/10/2023 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 5/24/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/24/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 6/5/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 6/5/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/17/2023 | Approved | JAVIER RAMOS JR |
| Final | 7/17/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 7/17/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/17/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 7/17/2023 | Approved | JAVIER RAMOS JR |
| Final | 8/22/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 8/22/2023 | Approved | JAVIER RAMOS JR |