6941 N NAGLE AVE 91605
Certificate Information: 6941 N NAGLE AVE 91605
- Application / Permit
- 21010-20000-06452
- Plan Check / Job No.
- B21VN17260
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 40'-0" X 33'-6" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 3/3/2022
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2021 | ARTIN ZARUKIAN |
| Corrections Issued | 12/21/2021 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 12/22/2021 | APPLICANT |
| Plan Check Approved | 3/3/2022 | ARTIN ZARUKIAN |
| Issued | 3/3/2022 | APPLICANT |
| CofO in Progress | 12/7/2022 | ARAM AVEDISIAN |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/23/2021 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 1/21/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 1/22/2022 | JOHN LIN |
| Hydrant and Access approval | Cleared | 2/19/2022 | CINDY JOSSELYN |
| Construction near power lines | Cleared | 2/28/2022 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C93320 | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/22/2022 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 4/26/2022 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 4/26/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 6/2/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 6/2/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 6/2/2022 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 6/2/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/8/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Shower Pan | 6/8/2022 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 6/13/2022 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 6/16/2022 | Partial Approval | RAFAEL CORTES |
| Green Building Rough | 6/16/2022 | Approved | RAFAEL CORTES |
| Interior/Exterior Lathing | 6/23/2022 | Approved | RAFAEL CORTES |
| Sewer | 8/19/2022 | Approved | ALAN MORELOS |
| Underground Mechanical | 8/19/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 9/29/2022 | Approved | RAFAEL CORTES |
| Drywall Nailing | 9/29/2022 | Approved | RAFAEL CORTES |
| ELECTRICAL-Final | 9/29/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 9/29/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 9/29/2022 | Approved | RAFAEL CORTES |
| HVAC-Final | 9/29/2022 | Approved | RAFAEL CORTES |
| PLUMBING-Final | 9/29/2022 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 9/29/2022 | SGSOV Approved | RAFAEL CORTES |
| Service/Power Release | 9/29/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Smoke Detectors | 9/29/2022 | Approved | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 9/29/2022 | Approved | RAFAEL CORTES |
| Service/Power Release | 9/30/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 10/5/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Service/Power Release | 10/5/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 11/23/2022 | Corrections Issued | ARAM AVEDISIAN |
| Service/Power Release | 11/23/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Final | 12/7/2022 | Approved | ARAM AVEDISIAN |
| Final | 12/7/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| PLUMBING-Final | 12/7/2022 | Approved | ARAM AVEDISIAN |
| Service/Power Release | 12/7/2022 | Approved | ARAM AVEDISIAN |