NEW 40'-0" X 33'-6" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 3/3/2022
Issuing Office
Current Status
CofO Issued on 12/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2021 APPLICANT
Assigned to Plan Check Engineer 12/21/2021 ARTIN ZARUKIAN
Corrections Issued 12/21/2021 ARTIN ZARUKIAN
Building Plans Picked Up 12/22/2021 APPLICANT
Plan Check Approved 3/3/2022 ARTIN ZARUKIAN
Issued 3/3/2022 APPLICANT
CofO in Progress 12/7/2022 ARAM AVEDISIAN
Permit Finaled 12/24/2022 MICHAEL SMITH
CofO Issued 12/24/2022 MICHAEL SMITH
Permit Finaled 12/24/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/22/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 12/23/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 12/23/2021 JOSE DUARTE-DIAZ
Low Impact Development Cleared 1/21/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 1/22/2022 JOHN LIN
Hydrant and Access approval Cleared 2/19/2022 CINDY JOSSELYN
Construction near power lines Cleared 2/28/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C93320       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/22/2022 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 4/26/2022 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 4/26/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 6/2/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 6/2/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 6/2/2022 Approved CHRISTOPHE COCHRAN
Wood Frame 6/2/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/8/2022 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 6/8/2022 Approved CHRISTOPHE COCHRAN
Insulation 6/13/2022 Approved CHRISTOPHE COCHRAN
Drywall Nailing 6/16/2022 Partial Approval RAFAEL CORTES
Green Building Rough 6/16/2022 Approved RAFAEL CORTES
Interior/Exterior Lathing 6/23/2022 Approved RAFAEL CORTES
Sewer 8/19/2022 Approved ALAN MORELOS
Underground Mechanical 8/19/2022 Approved ALAN MORELOS
BUILDING-Rough-Frame 9/29/2022 Approved RAFAEL CORTES
Drywall Nailing 9/29/2022 Approved RAFAEL CORTES
ELECTRICAL-Final 9/29/2022 Not Ready for Inspection RAFAEL CORTES
Final 9/29/2022 Not Ready for Inspection RAFAEL CORTES
Green Building Final 9/29/2022 Approved RAFAEL CORTES
HVAC-Final 9/29/2022 Approved RAFAEL CORTES
PLUMBING-Final 9/29/2022 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 9/29/2022 SGSOV Approved RAFAEL CORTES
Service/Power Release 9/29/2022 Not Ready for Inspection RAFAEL CORTES
Smoke Detectors 9/29/2022 Approved RAFAEL CORTES
Verify Sprinkler Sign Off 9/29/2022 Approved RAFAEL CORTES
Service/Power Release 9/30/2022 Not Ready for Inspection RAFAEL CORTES
Final 10/5/2022 Not Ready for Inspection RAFAEL CORTES
Service/Power Release 10/5/2022 Not Ready for Inspection RAFAEL CORTES
Final 11/23/2022 Corrections Issued ARAM AVEDISIAN
Service/Power Release 11/23/2022 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Final 12/7/2022 Approved ARAM AVEDISIAN
Final 12/7/2022 OK to Issue CofO ARAM AVEDISIAN
PLUMBING-Final 12/7/2022 Approved ARAM AVEDISIAN
Service/Power Release 12/7/2022 Approved ARAM AVEDISIAN