18912 W ERWIN ST 91335
Certificate Information: 18912 W ERWIN ST 91335
- Application / Permit
- 21010-20000-06441
- Plan Check / Job No.
- B21VN17215
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 26'-7" X 35'-5 DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) W/ 10' X 26'-7" ATTACHED PATIO COVER.
- Permit Issued
- Issued on 10/20/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2021 | RAPHAEL ROSAS |
| Corrections Issued | 12/25/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 1/10/2022 | APPLICANT |
| Applicant returned to address corrections | 9/29/2022 | JESSE ARELLANO |
| Plan Check Approved | 10/11/2022 | MOHAMMAD ESMAILI |
| Issued | 10/20/2022 | APPLICANT |
| CofO in Progress | 5/2/2024 | JON MCHUGH |
| Permit Finaled | 6/10/2024 | JOHN JANSON |
| CofO Issued | 6/10/2024 | JOHN JANSON |
| Permit Finaled | 6/10/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/5/2022 | DAGOVERTO GUERRERO |
| Watercourse | Cleared | 4/5/2022 | DAGOVERTO GUERRERO |
| ZI | Cleared | 5/6/2022 | DANG NGUYEN |
| Construction near power lines | Cleared | 7/6/2022 | TINA MIRANDA |
| Low Impact Development | Cleared | 9/19/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/19/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Djoneva,, Diana Ivanova; Lic. No.: C73805 | 3241 HENRIETTA AVE LA CRESCENTA, CA 91214 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/27/2022 | Corrections Issued | SEAN HAUPT |
| Pre-Inspection | 11/21/2022 | Partial Approval | SEAN WIRCH |
| PLUMBING-Rough | 12/5/2022 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 12/12/2022 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 12/20/2022 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 2/7/2023 | Not Ready for Inspection | SEAN HAUPT |
| Verify Sprinkler Sign Off | 2/7/2023 | Approved | SEAN HAUPT |
| Sewer | 5/10/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Sewer | 5/11/2023 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 6/13/2023 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 7/6/2023 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 7/6/2023 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 7/6/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 7/6/2023 | Corrections Issued | JON MCHUGH |
| Sewer | 7/6/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 7/26/2023 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 7/26/2023 | Corrections Issued | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 7/26/2023 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 7/26/2023 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 7/26/2023 | Approved | JUSTIN HAWLEY |
| Insulation | 8/1/2023 | Corrections Issued | JUSTIN HAWLEY |
| Insulation | 8/8/2023 | Approved | JEFFREY PARD |
| Drywall Nailing | 8/14/2023 | Conditional Approval | JUSTIN HAWLEY |
| Green Building Rough | 8/14/2023 | Corrections Issued | JUSTIN HAWLEY |
| Drywall Nailing | 8/29/2023 | Approved | MORRIS JACKSON |
| Green Building Rough | 8/29/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 8/29/2023 | Partial Approval | MORRIS JACKSON |
| Shower Pan | 9/12/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 9/25/2023 | Approved | JON MCHUGH |
| Final | 4/4/2024 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 4/4/2024 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 4/4/2024 | Not Required | JON MCHUGH |
| Smoke Detectors | 4/4/2024 | Approved | JON MCHUGH |
| Final | 4/8/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 4/8/2024 | Approved | JON MCHUGH |
| Final | 5/2/2024 | OK to Issue CofO | JON MCHUGH |