10221 N SOPHIA AVE 91343

Certificate Information: 10221 N SOPHIA AVE 91343

Application / Permit
21010-20000-06427
Plan Check / Job No.
B21VN17181
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) .
Permit Issued
Issued on 11/16/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2021 APPLICANT
Assigned to Plan Check Engineer 12/20/2021 ARTIN ZARUKIAN
Corrections Issued 12/20/2021 ARTIN ZARUKIAN
Building Plans Picked Up 12/21/2021 APPLICANT
Applicant returned to address corrections 11/7/2022 ALEC MOUSAKHANIAN
Applicant returned to address corrections 11/14/2022 RACHEL BEYENE
Plan Check Approved 11/15/2022 SHANGQIN XIE
Issued 11/16/2022 APPLICANT
CofO in Progress 8/8/2023 JAVIER RAMOS JR
Permit Finaled 9/15/2023 RUBEN SALAS
CofO Issued 9/15/2023 RUBEN SALAS
Permit Finaled 9/15/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/21/2021 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 12/23/2021 AMIR KASHFI
Sewer availability Cleared 12/23/2021 AMIR KASHFI
Roof/Waste drainage to street Cleared 4/11/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 8/29/2022 WALTER RAMIREZ
Hydrant and Access approval Cleared 10/21/2022 LAVEON RIDER
GPI Written Notices Cleared 11/7/2022 ARTIN ZARUKIAN
Grading Pre-Inspection Cleared 11/7/2022 ARTIN ZARUKIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/7/2022 Partial Approval JAVIER RAMOS JR
Sewer 12/7/2022 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 12/21/2022 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 1/4/2023 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 1/4/2023 Partial Approval JAVIER RAMOS JR
Green Building Rough 1/4/2023 Not Ready for Inspection JAVIER RAMOS JR
Sewer 1/4/2023 Not Ready for Inspection JAVIER RAMOS JR
Verify Sprinkler Sign Off 1/4/2023 Approved JAVIER RAMOS JR
Wood Frame 1/4/2023 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 1/24/2023 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 1/24/2023 Approved JAVIER RAMOS JR
Green Building Rough 1/24/2023 Approved JAVIER RAMOS JR
HVAC-Rough 1/24/2023 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 1/24/2023 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 1/24/2023 Approved JAVIER RAMOS JR
Shower Pan 1/24/2023 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Approved JOHN COLEMAN
HVAC-Rough 1/31/2023 Approved JOHN COLEMAN
Insulation 1/31/2023 Approved JOHN COLEMAN
Drywall Nailing 2/24/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 8/2/2023 Approved JAVIER RAMOS JR
Final 8/2/2023 OK to Issue CofO JAVIER RAMOS JR
Footing/Foundation/Slab 8/2/2023 Approved JAVIER RAMOS JR
Green Building Final 8/2/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/2/2023 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 8/2/2023 Approved JAVIER RAMOS JR
Smoke Detectors 8/2/2023 Approved JAVIER RAMOS JR