11647 N PASO ROBLES AVE 91344
Certificate Information: 11647 N PASO ROBLES AVE 91344
- Application / Permit
- 21010-20000-06404
- Plan Check / Job No.
- B21VN17104
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 24'X26' 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)-(d) WITH 45 SF COVERED PATIO. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/7/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | COLIN LOREDO |
| Corrections Issued | 12/21/2021 | COLIN LOREDO |
| Quality Review Completed | 12/23/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 12/27/2021 | APPLICANT |
| Plan Check Approved | 7/22/2022 | COLIN LOREDO |
| Issued | 9/7/2022 | APPLICANT |
| CofO in Progress | 1/2/2024 | STEVEN BACK |
| Permit Finaled | 1/11/2024 | JOHN JANSON |
| CofO Issued | 1/11/2024 | JOHN JANSON |
| Permit Finaled | 1/11/2024 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/13/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/26/2022 | CHRIS VONG |
| Address approval | Cleared | 7/12/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/12/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/13/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 7/22/2022 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 8/16/2022 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yogurtian,, Arpinee; Lic. No.: C49916 | 2529 FOOTHILL BLVD, STE 208 LA CRESCENTA, CA 91214 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/31/2022 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 10/31/2022 | Conditional Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 11/30/2022 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2023 | Corrections Issued | MORRIS JACKSON |
| Special/Order Compliance | 2/8/2023 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 2/27/2023 | Approved | SEAN HAUPT |
| Insulation | 3/31/2023 | Corrections Issued | SEAN WIRCH |
| Deputy Steel/Welding | 4/10/2023 | Conditional Approval | JEFFREY PARD |
| ELECTRICAL-Rough | 4/12/2023 | Corrections Issued | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2023 | Approved | SEAN HAUPT |
| HVAC-Rough | 4/12/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 4/12/2023 | Approved | SEAN HAUPT |
| Shower Pan | 4/12/2023 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 4/21/2023 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 4/21/2023 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 4/21/2023 | Approved | STEVEN BACK |
| Special/Order Compliance | 4/21/2023 | Partial Inspection | MORRIS JACKSON |
| ELECTRICAL-Rough | 5/19/2023 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2023 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 5/22/2023 | Corrections Issued | HORACE FULTZ |
| ELECTRICAL-Rough | 5/30/2023 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2023 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 6/8/2023 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 6/8/2023 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 6/8/2023 | Partial Approval | STEVEN BACK |
| Drywall Nailing | 6/27/2023 | Approved | STEVEN BACK |
| Insulation | 6/27/2023 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 6/27/2023 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 9/28/2023 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Final | 10/2/2023 | Corrections Issued | STEVEN BACK |
| Smoke Detectors | 10/2/2023 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 10/18/2023 | SGSOV Not Ready | JEFFREY BULL |
| Final | 10/24/2023 | Corrections Issued | STEVEN BACK |
| Green Building Final | 10/24/2023 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 10/24/2023 | SGSOV Not Ready | STEVEN BACK |
| Final | 11/3/2023 | Corrections Issued | STEVEN BACK |
| Green Building Final | 11/3/2023 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Not Ready | STEVEN BACK |
| Final | 12/12/2023 | Corrections Issued | STEVEN BACK |
| Green Building Final | 12/12/2023 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Approved | STEVEN BACK |
| Final | 1/2/2024 | OK to Issue CofO | STEVEN BACK |
| Service/Power Release | 1/2/2024 | Approved | STEVEN BACK |