22124 W DE LA OSA ST 91364
Certificate Information: 22124 W DE LA OSA ST 91364
- Application / Permit
- 21010-20000-06351
- Plan Check / Job No.
- B21VN16987
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRR. SHAPED 16'-7" x 40' ONE-STORY DET. ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g); ALL WORK PER ENGINEERING DESIGN
- Permit Issued
- Issued on 6/28/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2022 | SEAN SHAHMIRI |
| Corrections Issued | 1/26/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 2/4/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 2/7/2022 | APPLICANT |
| Applicant returned to address corrections | 6/26/2023 | SEAN SHAHMIRI |
| Plan Check Approved | 6/26/2023 | SEAN SHAHMIRI |
| Issued | 6/28/2023 | APPLICANT |
| CofO in Progress | 2/25/2025 | JOHN HAYES |
| CofO Issued | 3/26/2025 | JOHN JANSON |
| Permit Finaled | 3/26/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 8/15/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 8/26/2022 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 5/9/2023 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/11/2023 | MEGAN GODINEZ |
| Specific Plan | Cleared | 5/31/2023 | OLGA AYALA |
| Construction within easement | Cleared | 6/21/2023 | TINA MIRANDA |
Contact Information
| Contractor | E&E Construction Inc; Lic. No.: 1087571-B | 19111 HAMLIN STREET #8 RESEDA, CA 91335 |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/2/2023 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 8/8/2023 | Corrections Issued | JOHN KIDWELL |
| Green Building Rough | 8/8/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/31/2023 | Corrections Issued | PETER FOLLING |
| Footing/Foundation/Slab | 9/5/2023 | Conditional Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/4/2023 | Corrections Issued | PETER FOLLING |
| Green Building Rough | 10/4/2023 | Not Ready for Inspection | PETER FOLLING |
| Verify Sprinkler Sign Off | 10/4/2023 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2023 | Approved | PETER FOLLING |
| Footing/Foundation/Slab | 10/12/2023 | Approved | PETER FOLLING |
| PLUMBING-Rough | 10/12/2023 | Approved | PETER FOLLING |
| Verify Sprinkler Sign Off | 10/12/2023 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 10/23/2023 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 10/27/2023 | Partial Approval | PETER FOLLING |
| Interior/Exterior Lathing | 11/2/2023 | Partial Approval | PETER FOLLING |
| ELECTRICAL-Rough | 11/22/2023 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 12/4/2023 | Corrections Issued | JOHN KIDWELL |
| PLUMBING-Rough | 12/4/2023 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 12/11/2023 | Approved | JOHN KIDWELL |
| Drywall Nailing | 12/11/2023 | Approved | JOHN KIDWELL |
| Green Building Rough | 12/11/2023 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 12/11/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 12/12/2023 | Not Ready for Inspection | MORRIS JACKSON |
| Interior/Exterior Lathing | 1/2/2024 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Final | 3/7/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Service/Power Release | 3/7/2024 | Approved | MORRIS JACKSON |
| Final | 8/9/2024 | Corrections Issued | JOHN HAYES |
| Green Building Final | 8/9/2024 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/9/2024 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 8/9/2024 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 10/7/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 10/7/2024 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/7/2024 | SGSOV Not Ready | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/19/2024 | SGSOV Not Ready | JOHN HAYES |
| Final | 12/30/2024 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/30/2024 | SGSOV Not Required | JOHN HAYES |
| Final | 2/18/2025 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/25/2025 | OK to Issue CofO | JOHN HAYES |