4005 N ALCOVE AVE 91604
Certificate Information: 4005 N ALCOVE AVE 91604
- Application / Permit
- 21010-20000-06347
- Plan Check / Job No.
- B21VN16977
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 16'-1" X 14'-6" DETACHED REC ROOM PER ENGINEER
- Permit Issued
- Issued on 4/21/2022
- Issuing Office
- Current Status
- CofO Issued on 9/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 12/9/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/16/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/5/2022 | APPLICANT |
| Issued | 4/21/2022 | APPLICANT |
| CofO in Progress | 9/1/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 9/3/2022 | DEROLD HAUFF |
| CofO Issued | 9/3/2022 | DEROLD HAUFF |
| Permit Finaled | 9/3/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/11/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2021 | DAGOVERTO GUERRERO |
| ZI | Cleared | 12/13/2021 | MIGUEL GAMBOA |
| Construction near power lines | Cleared | 3/4/2022 | TINA MIRANDA |
| Grading Pre-Inspection | Cleared | 3/16/2022 | JEROME MAGAT PALMA |
Contact Information
| Contractor | E Z Builders Group Inc; Lic. No.: 792026-B | P O BOX 1844 STUDIO CITY, CA 91614 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/25/2022 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 5/25/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/15/2022 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 6/15/2022 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 6/15/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 6/17/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 6/24/2022 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 6/24/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/24/2022 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 6/30/2022 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 8/11/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 8/11/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 8/11/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Final | 8/11/2022 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 8/11/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 8/11/2022 | Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 8/11/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 9/1/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |