2656 1/2 E ROSEVIEW AVE 90065

Certificate Information: 2656 1/2 E ROSEVIEW AVE 90065

Application / Permit
21010-20000-06335
Plan Check / Job No.
B21VN16889
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 1-STORY SFD (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 2/23/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2022 COLIN LOREDO
Corrections Issued 1/25/2022 COLIN LOREDO
Quality Review Completed 2/4/2022 OMID HEDAYAT
Building Plans Picked Up 2/8/2022 APPLICANT
Applicant returned to address corrections 6/6/2022 COLIN LOREDO
Applicant returned to address corrections 7/12/2022 COLIN LOREDO
Applicant returned to address corrections 1/5/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 1/16/2024 NILOOFAR MEHRAIN
Plan Check Approved 1/23/2024 NILOOFAR MEHRAIN
Issued 2/23/2024 APPLICANT
CofO in Progress 5/22/2025 ALIZAH MAYAGOITIA
Permit Finaled 5/25/2025 DEROLD HAUFF
CofO Issued 5/25/2025 DEROLD HAUFF
Permit Finaled 5/25/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/4/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 3/9/2022 AMAAN MALIK
Sewer availability Cleared 3/9/2022 AMAAN MALIK
Hydrant and Access approval Cleared 6/17/2022 KURT CORRAL
Grading Pre-Inspection Cleared 7/12/2022 MATTHEW JENKINS
GPI Written Notices Cleared 1/5/2023 COLIN LOREDO
Low Impact Development Cleared 1/17/2023 LONDY ALVARADO
Roof/Waste drainage to street Cleared 2/1/2023 WALLIE JONG
ZI Cleared 1/5/2024 BRENNEN OBETO
ZI Cleared 1/5/2024 BRENNEN OBETO

Contact Information

Contractor Owner-Builder       ,
Engineer Truong,, Phong; Lic. No.: C70784 20439 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/5/2024 Partial Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/23/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 5/6/2024 Approved OSVALDO PARAMO
PLUMBING-Rough 5/6/2024 Partial Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 6/4/2024 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Approved OSVALDO PARAMO
PLUMBING-Rough 7/1/2024 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 8/13/2024 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 8/13/2024 Approved OSVALDO PARAMO
ELECTRICAL-Rough 10/15/2024 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 10/18/2024 Approved OSVALDO PARAMO
Green Building Rough 10/18/2024 Approved OSVALDO PARAMO
Interior/Exterior Lathing 10/18/2024 Partial Approval OSVALDO PARAMO
Verify Sprinkler Sign Off 10/18/2024 Approved OSVALDO PARAMO
Insulation 10/31/2024 Corrections Issued WILLIAM SIERRA
HVAC-Rough 11/18/2024 Corrections Issued ANTHONY RAMOS
Insulation 11/18/2024 Partial Approval ANTHONY RAMOS
HVAC-Rough 11/26/2024 Approved OSVALDO PARAMO
Insulation 11/26/2024 Approved OSVALDO PARAMO
Drywall Nailing 12/6/2024 Approved OSVALDO PARAMO
Shower Pan 1/3/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 2/4/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 2/4/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 2/4/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 2/4/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/4/2025 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 2/4/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 2/4/2025 Approved ALIZAH MAYAGOITIA
Final 2/11/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 2/11/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 2/11/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 2/25/2025 Corrections Issued ALIZAH MAYAGOITIA
Service/Power Release 2/25/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 5/22/2025 Approved ALIZAH MAYAGOITIA
Final 5/22/2025 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 5/22/2025 Approved ALIZAH MAYAGOITIA