13041 W ROSE AVE 90066

Certificate Information: 13041 W ROSE AVE 90066

Application / Permit
21010-20000-06332
Plan Check / Job No.
B21VN16875
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 44' X 65'-7" TWO STORY SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-R FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 2/9/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2022 SELLA BENYAMIN
Corrections Issued 1/25/2022 SELLA BENYAMIN
Quality Review Completed 2/1/2022 STEVEN KIM
Building Plans Picked Up 2/2/2022 APPLICANT
Applicant returned to address corrections 9/27/2022 SELLA BENYAMIN
Plan Check Approved 2/9/2023 SELLA BENYAMIN
Issued 2/9/2023 APPLICANT
CofO in Progress 9/2/2025 WILBER ROSALES
No Progress 9/2/2025 DAVID FEILER
CofO in Progress 9/2/2025 DAVID FEILER
Permit Finaled 9/5/2025 RICHARD STEINBACH
CofO Issued 9/5/2025 RICHARD STEINBACH
Permit Finaled 9/5/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/7/2022 SAUL GARCIA
Sewer availability Cleared 2/7/2022 SAUL GARCIA
Hydrant and Access approval Cleared 10/1/2022 RUEL COLE
Low Impact Development Cleared 10/6/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/6/2022 SAUL GARCIA
GPI Written Notices Cleared 2/9/2023 SELLA BENYAMIN
Grading Pre-Inspection Cleared 2/9/2023 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 6/12/2024 Corrections Issued JESUS RODRIGUEZ
Piling/Pier/Caisson 7/2/2024 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 8/5/2024 Partial Approval JESUS RODRIGUEZ
Special/Order Compliance 9/20/2024 Corrections Issued JESUS PINEDA
Underground Mechanical 9/20/2024 Corrections Issued JESUS PINEDA
PLUMBING-Rough 9/27/2024 Partial Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 10/4/2024 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 10/4/2024 Not Ready for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 10/15/2024 Approved JESUS PINEDA
Footing/Foundation/Slab 10/15/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Corrections Issued JESUS PINEDA
Deputy Steel/Welding 11/14/2024 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/2/2024 Partial Approval EVAN COOPER
ELECTRICAL-Rough 12/26/2024 Conditional Approval JESUS PINEDA
HVAC-Rough 12/26/2024 Approved JESUS PINEDA
PLUMBING-Rough 12/26/2024 Approved JESUS PINEDA
Deputy Wood Construction 12/27/2024 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 1/2/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 1/2/2025 Corrections Issued JESUS PINEDA
Special/Order Compliance 1/2/2025 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 1/6/2025 Approved JESUS PINEDA
Green Building Rough 1/6/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 1/6/2025 Partial Approval JESUS PINEDA
Special/Order Compliance 1/6/2025 Corrections Issued JESUS PINEDA
Verify Sprinkler Sign Off 1/6/2025 Approved JESUS PINEDA
Shower Pan 1/13/2025 Approved JESUS PINEDA
Insulation 1/15/2025 Corrections Issued JAYLIN GRAVITTE
Special/Order Compliance 1/15/2025 Partial Inspection BOBBY KEY
Insulation 1/21/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 1/22/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 1/27/2025 Approved JESUS PINEDA
Sewer 5/28/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 7/29/2025 Approved WILBER ROSALES
Final 7/29/2025 Corrections Issued WILBER ROSALES
Green Building Final 7/29/2025 Approved WILBER ROSALES
HVAC-Final 7/29/2025 Corrections Issued WILBER ROSALES
PLUMBING-Final 7/29/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 7/29/2025 SGSOV Approved WILBER ROSALES
Service/Power Release 7/29/2025 Not Ready for Inspection WILBER ROSALES
Smoke Detectors 7/29/2025 Approved WILBER ROSALES
HVAC-Final 8/19/2025 Approved WILBER ROSALES
Service/Power Release 8/19/2025 Not Ready for Inspection WILBER ROSALES
Final 8/20/2025 Partial Inspection WILBER ROSALES
Final 8/21/2025 Corrections Issued WILBER ROSALES
Service/Power Release 8/21/2025 Not Ready for Inspection WILBER ROSALES
Final 8/29/2025 OK to Issue CofO WILBER ROSALES
Service/Power Release 8/29/2025 Approved WILBER ROSALES