4917 N MAMMOTH AVE 91423

Certificate Information: 4917 N MAMMOTH AVE 91423

Application / Permit
21010-20000-06294
Plan Check / Job No.
B21VN16791
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 26'2" X 18'6" DETACHED ONE STORY ACCESSORY DWELLING UNIT AS PER GCS 65852.2(E)(1)(B), NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/26/2022
Issuing Office
Current Status
CofO Issued on 6/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2021 APPLICANT
Assigned to Plan Check Engineer 1/6/2022 RARES BODEA
Corrections Issued 1/19/2022 RARES BODEA
Quality Review Completed 1/21/2022 STEVEN KIM
Applicant returned to address corrections 5/11/2022 RARES BODEA
Plan Check Approved 5/26/2022 RARES BODEA
Issued 5/26/2022 APPLICANT
CofO in Progress 5/11/2023 JUAN VALENZUELA
Permit Finaled 6/9/2023 MICHAEL SMITH
CofO Issued 6/9/2023 MICHAEL SMITH
Permit Finaled 6/9/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/1/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/1/2022 LEE GUILBEAUX
Sewer availability Cleared 2/1/2022 LEE GUILBEAUX
Construction near power lines Cleared 2/10/2022 WALTER RAMIREZ
Construction within easement Cleared 2/10/2022 WALTER RAMIREZ
ZI Cleared 2/22/2022 LAUREN PADICK
Low Impact Development Cleared 3/22/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 4/4/2022 LEE GUILBEAUX
Hydrant and Access approval Cleared 4/5/2022 LAURINDA MEADE

Contact Information

Contractor H C Builders Inc; Lic. No.: 1017411-B 17328 VENTURA BLVD #130      ENCINO, CA 91316
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/15/2022 Partial Approval MISAEL ESPARZA
Sewer 6/15/2022 Corrections Issued MISAEL ESPARZA
Sewer 6/22/2022 Approved JACK KARGODORIAN
Footing/Foundation/Slab 6/30/2022 Approved MATT KELLERMAN
PLUMBING-Rough 9/7/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 9/12/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 9/12/2022 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 9/12/2022 Approved MISAEL ESPARZA
ELECTRICAL-Rough 9/15/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/15/2022 Corrections Issued MISAEL ESPARZA
HVAC-Rough 9/15/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 9/21/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 9/21/2022 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 9/21/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 9/21/2022 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 9/21/2022 Approved MISAEL ESPARZA
ELECTRICAL-Rough 9/23/2022 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/23/2022 Partial Approval MISAEL ESPARZA
Shower Pan 9/28/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 10/12/2022 Partial Approval MISAEL ESPARZA
Insulation 10/19/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/1/2022 Approved MISAEL ESPARZA
Drywall Nailing 11/3/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 3/30/2023 Corrections Issued MISAEL ESPARZA
HVAC-Final 3/30/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 3/30/2023 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 4/10/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 4/10/2023 Corrections Issued MISAEL ESPARZA
Final 4/10/2023 Corrections Issued MISAEL ESPARZA
Green Building Final 4/10/2023 Approved MISAEL ESPARZA
Green Building Rough 4/10/2023 Approved MISAEL ESPARZA
HVAC-Final 4/10/2023 Approved MISAEL ESPARZA
PLUMBING-Final 4/10/2023 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/10/2023 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 4/10/2023 Not Required MISAEL ESPARZA
Smoke Detectors 4/10/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 4/17/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 4/17/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 5/10/2023 Approved JUAN VALENZUELA
Final 5/10/2023 OK to Issue CofO JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 5/10/2023 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 5/10/2023 Approved JUAN VALENZUELA