4621 N NOBLE AVE 91403

Certificate Information: 4621 N NOBLE AVE 91403

Application / Permit
21010-20000-06287
Plan Check / Job No.
B21VN16774
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 61' X 38' TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/24/2022
Issuing Office
Current Status
CofO Issued on 10/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 SELLA BENYAMIN
Corrections Issued 12/21/2021 SELLA BENYAMIN
Quality Review Completed 12/23/2021 STEVEN KIM
Building Plans Picked Up 1/3/2022 APPLICANT
Plan Check Approved 3/23/2022 SELLA BENYAMIN
Issued 3/24/2022 APPLICANT
CofO in Progress 10/17/2022 JACK KARGODORIAN
Permit Finaled 10/26/2022 RONALD MYRICK
CofO Issued 10/26/2022 RONALD MYRICK
Permit Finaled 10/26/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 1/12/2022 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 1/13/2022 AMIR KASHFI
Sewer availability Cleared 1/13/2022 AMIR KASHFI
Trees in Parkway Cleared 2/2/2022 ADALBERTO VERA
Low Impact Development Cleared 2/25/2022 TA ANH
Hydrant and Access approval Cleared 2/28/2022 LAURINDA MEADE
Permit Cleared 3/1/2022 AMIR KASHFI
Roof/Waste drainage to street Cleared 3/1/2022 AMIR KASHFI

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/7/2022 Partial Approval JACK KARGODORIAN
Deputy Reinf. Concrete 4/18/2022 Approved JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 4/18/2022 Approved JACK KARGODORIAN
Footing/Foundation/Slab 4/18/2022 Approved JACK KARGODORIAN
Deputy Reinf. Concrete 4/19/2022 Partial Approval JACK KARGODORIAN
Deputy Drilled-In Anchors 4/21/2022 Partial Approval JACK KARGODORIAN
Deputy Reinf. Concrete 4/21/2022 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 4/26/2022 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 4/26/2022 Partial Approval JACK KARGODORIAN
Green Building Rough 4/26/2022 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 4/26/2022 Not Ready for Inspection JACK KARGODORIAN
Deputy Wood Construction 5/12/2022 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 5/16/2022 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Partial Approval JACK KARGODORIAN
Green Building Rough 5/16/2022 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 5/16/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 5/16/2022 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 5/16/2022 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 5/24/2022 Approved JACK KARGODORIAN
ELECTRICAL-Rough 5/24/2022 Approved JACK KARGODORIAN
Green Building Rough 5/24/2022 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 5/24/2022 Approved JACK KARGODORIAN
Deputy Steel/Welding 5/25/2022 Partial Approval JACK KARGODORIAN
Insulation 5/31/2022 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 5/31/2022 Partial Approval JACK KARGODORIAN
Shower Pan 5/31/2022 Approved JACK KARGODORIAN
Insulation 6/2/2022 Approved JACK KARGODORIAN
Drywall Nailing 6/14/2022 Approved JACK KARGODORIAN
Final 9/7/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 9/7/2022 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Approved JACK KARGODORIAN
Service/Power Release 9/7/2022 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 9/7/2022 Not Ready for Inspection JACK KARGODORIAN
Final 9/29/2022 Corrections Issued DAVID ANDERSON
Green Building Final 9/29/2022 Approved DAVID ANDERSON
Service/Power Release 9/29/2022 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 9/29/2022 Approved DAVID ANDERSON
ELECTRICAL-Final 10/6/2022 Approved JACK KARGODORIAN
Final 10/6/2022 Corrections Issued JACK KARGODORIAN
HVAC-Final 10/6/2022 Approved JACK KARGODORIAN
PLUMBING-Final 10/6/2022 Approved JACK KARGODORIAN
Service/Power Release 10/6/2022 Not Ready for Inspection JACK KARGODORIAN
Final 10/17/2022 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 10/17/2022 Approved JACK KARGODORIAN