4621 N NOBLE AVE 91403
Certificate Information: 4621 N NOBLE AVE 91403
- Application / Permit
- 21010-20000-06287
- Plan Check / Job No.
- B21VN16774
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 61' X 38' TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 3/24/2022
- Issuing Office
- Current Status
- CofO Issued on 10/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | SELLA BENYAMIN |
| Corrections Issued | 12/21/2021 | SELLA BENYAMIN |
| Quality Review Completed | 12/23/2021 | STEVEN KIM |
| Building Plans Picked Up | 1/3/2022 | APPLICANT |
| Plan Check Approved | 3/23/2022 | SELLA BENYAMIN |
| Issued | 3/24/2022 | APPLICANT |
| CofO in Progress | 10/17/2022 | JACK KARGODORIAN |
| Permit Finaled | 10/26/2022 | RONALD MYRICK |
| CofO Issued | 10/26/2022 | RONALD MYRICK |
| Permit Finaled | 10/26/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 1/12/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 1/13/2022 | AMIR KASHFI |
| Trees in Parkway | Cleared | 2/2/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 2/25/2022 | TA ANH |
| Hydrant and Access approval | Cleared | 2/28/2022 | LAURINDA MEADE |
| Permit | Cleared | 3/1/2022 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 3/1/2022 | AMIR KASHFI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/7/2022 | Partial Approval | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 4/18/2022 | Approved | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 4/18/2022 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 4/18/2022 | Approved | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 4/19/2022 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 4/21/2022 | Partial Approval | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 4/21/2022 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/26/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2022 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 4/26/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 4/26/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Deputy Wood Construction | 5/12/2022 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 5/16/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 5/16/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 5/16/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 5/16/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 5/16/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/24/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 5/24/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 5/24/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 5/24/2022 | Approved | JACK KARGODORIAN |
| Deputy Steel/Welding | 5/25/2022 | Partial Approval | JACK KARGODORIAN |
| Insulation | 5/31/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 5/31/2022 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 5/31/2022 | Approved | JACK KARGODORIAN |
| Insulation | 6/2/2022 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 6/14/2022 | Approved | JACK KARGODORIAN |
| Final | 9/7/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 9/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 9/7/2022 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 9/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 9/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 9/29/2022 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 9/29/2022 | Approved | DAVID ANDERSON |
| Service/Power Release | 9/29/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 9/29/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 10/6/2022 | Approved | JACK KARGODORIAN |
| Final | 10/6/2022 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Final | 10/6/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 10/6/2022 | Approved | JACK KARGODORIAN |
| Service/Power Release | 10/6/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 10/17/2022 | OK to Issue CofO | JACK KARGODORIAN |
| Service/Power Release | 10/17/2022 | Approved | JACK KARGODORIAN |