819 N OGDEN DR 90046

Certificate Information: 819 N OGDEN DR 90046

Application / Permit
21010-20000-06278
Plan Check / Job No.
B21VN16717
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 80'-0" X 38'-0" IRREGULAR SHAPED 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ROOF DECK. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/30/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 COLIN LOREDO
Corrections Issued 12/21/2021 COLIN LOREDO
Quality Review Completed 12/22/2021 OMID HEDAYAT
Building Plans Picked Up 1/3/2022 APPLICANT
Applicant returned to address corrections 4/15/2022 COLIN LOREDO
Plan Check Approved 4/26/2022 COLIN LOREDO
Issued 8/30/2022 APPLICANT
CofO in Progress 1/4/2024 BRENDAN MORELLI
Permit Finaled 1/7/2024 DEROLD HAUFF
CofO Issued 1/7/2024 DEROLD HAUFF
Permit Finaled 1/7/2024 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 1/10/2022 CHRIS VONG
Trees in Parkway Cleared 2/25/2022 ADALBERTO VERA
Address approval Cleared 3/19/2022 CINDY QI
Permit Cleared 3/19/2022 CINDY QI
Roof/Waste drainage to street Cleared 3/19/2022 CINDY QI
Sewer availability Cleared 3/19/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 3/22/2022 CINDY QI
Hydrant and Access approval Cleared 4/22/2022 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/28/2022 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 10/5/2022 Corrections Issued MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 10/11/2022 Approved MICHAEL LEWIS
Deputy Reinf. Concrete 10/14/2022 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/28/2022 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/9/2022 Conditional Approval MICHAEL LEWIS
ELECTRICAL-Rough 12/19/2022 Approved MICHAEL LEWIS
HVAC-Rough 12/19/2022 Approved MICHAEL LEWIS
PLUMBING-Rough 12/19/2022 Approved MICHAEL LEWIS
Deputy Wood Construction 12/27/2022 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 1/13/2023 Not Ready for Inspection MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 1/13/2023 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 1/13/2023 Approved MICHAEL LEWIS
Green Building Rough 2/2/2023 Approved MICHAEL LEWIS
Insulation 2/2/2023 Partial Approval MICHAEL LEWIS
Interior/Exterior Lathing 2/2/2023 Approved MICHAEL LEWIS
Drywall Nailing 3/20/2023 Corrections Issued MICHAEL LEWIS
Insulation 3/20/2023 Corrections Issued MICHAEL LEWIS
BUILDING-Rough-Frame 3/23/2023 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 3/28/2023 Partial Approval MICHAEL LEWIS
Drywall Nailing 3/28/2023 Approved MICHAEL LEWIS
Insulation 3/28/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 8/23/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 8/23/2023 Not Ready for Inspection LILIANA PORTILLO
Final 8/23/2023 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 8/23/2023 Approved LILIANA PORTILLO
Green Building Final 8/23/2023 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 8/23/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 8/23/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 8/23/2023 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 8/23/2023 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 8/23/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 9/1/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 9/11/2023 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 9/11/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 9/14/2023 Corrections Issued LILIANA PORTILLO
Service/Power Release 9/14/2023 Corrections Issued LILIANA PORTILLO
Service/Power Release 9/20/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 12/7/2023 Approved LILIANA PORTILLO
Final 12/7/2023 Corrections Issued LILIANA PORTILLO
Green Building Final 12/7/2023 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 12/7/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 12/7/2023 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/7/2023 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 12/7/2023 Approved LILIANA PORTILLO
Final 1/3/2024 OK to Issue CofO BRENDAN MORELLI
Green Building Final 1/3/2024 Approved BRENDAN MORELLI