6533 N BEN AVE 91606
Certificate Information: 6533 N BEN AVE 91606
- Application / Permit
- 21010-20000-06269
- Plan Check / Job No.
- B21VN16694
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 29'-4" X 48'-6" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/15/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | RAPHAEL ROSAS |
| Corrections Issued | 12/9/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/22/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/14/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 7/8/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 7/12/2022 | APPLICANT |
| Issued | 9/15/2022 | APPLICANT |
| CofO in Progress | 4/12/2023 | JOHN HAYES |
| CofO Issued | 4/18/2023 | MICHAEL SMITH |
| Permit Finaled | 4/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/5/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 2/10/2022 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 2/10/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 4/2/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Marentes Construction; Lic. No.: 961891-B | 38732 GLENBUSH AVE PALMDALE, CA 93550 |
| Engineer | Galbreath,, Sean; Lic. No.: S5653 | 600 SOUTH LAKE AVE STE 308 PASADENA, CA 91106 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/26/2022 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 9/30/2022 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 9/30/2022 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 10/5/2022 | Approved | JOHN HAYES |
| Pre-Inspection | 10/5/2022 | Approved | JOHN HAYES |
| PLUMBING-Rough | 10/14/2022 | Approved | JOHN HAYES |
| Wood Frame | 10/14/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Not Ready for Inspection | ROBERT GOLD |
| Insulation | 10/18/2022 | Not Ready for Inspection | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2022 | Not Ready for Inspection | JOHN HAYES |
| Sewer | 10/31/2022 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 11/22/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/22/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 11/22/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 11/22/2022 | Conditional Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/22/2022 | Approved | ARAM AVEDISIAN |
| Shower Pan | 11/22/2022 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 11/22/2022 | Approved | ARAM AVEDISIAN |
| Wood Frame | 11/22/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/28/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 12/2/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 12/2/2022 | Partial Approval | JOHN HAYES |
| Drywall Nailing | 12/8/2022 | Approved | JORDAN KUTZLY |
| Interior/Exterior Lathing | 12/8/2022 | Approved | JORDAN KUTZLY |
| ELECTRICAL-Final | 3/8/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 3/8/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/8/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 3/8/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 3/8/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/8/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/8/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 3/8/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 3/8/2023 | Approved | JENNIFER RABUCHIN |
| Final | 3/16/2023 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 3/16/2023 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 3/16/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 3/23/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Service/Power Release | 3/23/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 4/11/2023 | OK to Issue CofO | JOHN HAYES |
| Service/Power Release | 4/11/2023 | Approved | JOHN HAYES |