6463 N WOODLAKE AVE 91307
Certificate Information: 6463 N WOODLAKE AVE 91307
- Application / Permit
- 21010-20000-06249
- Plan Check / Job No.
- B21VN16661
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT EXISTING DETACHED 2-CAR GARAGE TO A NEW ACCESSORY DWELLING UNIT per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/8/2022
- Issuing Office
- Current Status
- CofO Corrected on 1/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2021 | MONICA RAMIREZ |
| Corrections Issued | 12/6/2021 | MONICA RAMIREZ |
| Plan Check Approved | 1/6/2022 | DANIEL YIP |
| Issued | 3/8/2022 | APPLICANT |
| CofO in Progress | 12/28/2022 | TROY SANDERS |
| Re-Activate Permit | 1/5/2023 | JOHN JANSON |
| CofO Issued-Status Void | 1/5/2023 | JOHN JANSON |
| Permit Finaled-Status Void | 1/5/2023 | JOHN JANSON |
| CofO Corrected | 1/5/2023 | JOHN JANSON |
| Permit Finaled | 1/5/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/15/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/15/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2021 | CARLOS AGUILERA |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: NA24587 | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/31/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 4/20/2022 | Approved | TROY SANDERS |
| Green Building Rough | 4/20/2022 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 4/26/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 4/26/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/10/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 5/10/2022 | Not Ready for Inspection | TROY SANDERS |
| Gas Test | 5/10/2022 | Approved | TROY SANDERS |
| Green Building Rough | 5/10/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 5/10/2022 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 5/10/2022 | Approved | TROY SANDERS |
| Sewer | 5/10/2022 | Approved | TROY SANDERS |
| Insulation | 5/11/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 5/16/2022 | Not Ready for Inspection | JESUS PINEDA |
| Drywall Nailing | 5/27/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 5/27/2022 | Partial Approval | TROY SANDERS |
| Final | 10/12/2022 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 10/12/2022 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/12/2022 | SGSOV Not Ready | TROY SANDERS |
| Smoke Detectors | 10/12/2022 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Final | 12/1/2022 | Not Ready for Inspection | HENRY KIM |
| Final | 12/1/2022 | Corrections Issued | HENRY KIM |
| HVAC-Final | 12/1/2022 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Final | 12/1/2022 | Not Ready for Inspection | HENRY KIM |
| Smoke Detectors | 12/1/2022 | Corrections Issued | HENRY KIM |
| Special/Order Compliance | 12/1/2022 | Partial Inspection | JESUS PINEDA |
| Final | 12/15/2022 | Corrections Issued | TROY SANDERS |
| Green Building Final | 12/15/2022 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/15/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 12/15/2022 | Approved | TROY SANDERS |
| Final | 12/28/2022 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 12/28/2022 | Approved | TROY SANDERS |